INVL-linked issuer REFI Blue launches €10 million bond offering for Dolj solar

Bond terms for REFI Blue’s refinancing

A company linked to Lithuania’s INVL Asset Management has launched a public bond offering to refinance short-term debt tied to a solar power project in southwestern Romania. The issuing entity is REFI Blue, which is owned by INVL Renewable Energy Fund I. The bond sale targets gross proceeds of €10 million.

The funds are intended to refinance financing for a 60 MW solar power plant in Dolj County. The facility has been completed and connected to the electricity grid, with electricity supply under operational testing. Final licensing procedures are still ongoing .

Maturity, pricing range and investor access

The bonds are scheduled to mature on 22 December 2028. The final yield is expected to be in the 8–9% range, with the exact level set through an auction process. The minimum investment is set at €1,000.

The offering period runs from 27 May to 17 June. It is open to both retail and institutional investors across the Baltic region. After issuance, the bonds are expected to be listed on the Nasdaq Vilnius First North market .

Guarantee and role of Artea Bank

The transaction is backed by a guarantee from INVL Renewable Energy Fund I. Artea Bank is serving as lead arranger and distributor for the bond offering. The company states that the Romanian solar facility covers around 67 hectares.

INVL Renewable Energy Fund I also develops renewable energy projects across Romania and Poland. Its combined project pipeline totals approximately 389 MW. During operational testing, the Dolj solar plant is already supplying electricity while licensing work continues .

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania seeks to extend emergency power controls as supply risks persist

Romania is seeking to extend its emergency electricity-market powers through October 31, maintaining the option to restrict exports or limit industrial consumption if prolonged nuclear and hydropower constraints threaten security of supply. Under the proposed extension, transmission system operator Transelectrica...

Romania transforms telecom backup batteries into virtual power plant

Romania is testing whether thousands of backup batteries installed at telecommunications sites can be transformed from emergency infrastructure into a distributed virtual power plant capable of generating revenue in electricity flexibility markets. Huawei Romania, Bamboo Energy and Flexumers are developing...

Rezolv Energy commissions 192 MW first phase of Vifor wind farm in Romania

Vifor project capacity and turbine configuration Rezolv Energy has commissioned the 192 MW first phase of its Vifor wind farm in Romania. The project is located in Buzău County. The first phase uses 30 Vestas V162 EnVentus turbines, each rated...
Supported byVirtu Energy