The Administrative Court in Ljubljana annulled the decision of the Slovenian Government, according to which, the public interest in the field of renewable energy sources is above the interest for nature protection within the procedure of issuing of building permit for the hydropower plant Mokrice, the last in the series of HPPs on the Sava river. In 2019, the Court already annulled the building permit issued by the Slovenian Environmental Agency (ARSO).

The Court assessed that the entire Environmental Impact Assessment (EIA) procedure must be carried out before initiating the public interest procedure. The project’s investor HESS, a part of GEN Group, hopes that the repeated procedure for determining the predominance of the public interest will be carried out as soon as possible, in order to obtain a building permit as soon as possible.

HPP Mokrice project envisages that the new 28.05 MW HPP should have water inflow of 500 cubic meters per second and that its annual electricity generation should amount to 128 GWh. Estimated cost of the project is around 177 million euros. The construction was supposed to start by the end of 2019 and the plant should have been completed in mid-2022. In September 2017, 45 MW HPP Brezice, fourth of the five planned HPPs in the lower Sava project, has been officially commissioned.

Last year, HESS signed a 19 million euros worth contract with local company Litostroj Power, owned by Czech Energo-Pro, on the supply of equipment for HPP Mokrice project.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia tests smart meters and EV charging as drivers of electricity flexibility

Slovenia is emerging as a key testing ground in Southeast Europe for how smart meters, dynamic network tariffs and automated electric-vehicle charging can transform ordinary electricity consumers into flexible power-market assets. Recent Slovenian pilots have demonstrated that EV charging can...

Slovenia net generation down 13% in August as imports increase

Slovenia’s net electricity generation fell 13% year on year in August to 919 GWh. Production was also 7% lower than in July. The month’s figures were accompanied by higher cross-border electricity movements. Conventional and nuclear output changes Thermal generation declined 42%...

Slovenia electricity demand up 8% in August, exceeding 2026 plan

Slovenian electricity consumption increased by more than 8% year on year in August, keeping overall demand ahead of the 2026 system plan. The latest figures also point to a higher likelihood that annual consumption will surpass the original 11...
Supported byVirtu Energy