Paks II, the project company to upgrade Hungary’s only commercial nuclear power plant, is speeding up the preparation of a response to a request from the National Atomic Energy Office (OAH) for further clarification on the licensing procedure for the two new units.

This news was confirmed by Alexander Merten, Deputy Director of ASE, Rosatom’s general contractor, in an interview published in the Hungarian business daily Vilaggazdasag.

“We will provide the requested information and answers as soon as possible,” Merten said.
The OAH had until the end of September to issue an implementation permit for the two blocks, but said in October that it had requested “further clarifications” for the procedure.

The office said the documentation submitted by Pax II was “very thorough in some respects”, but added that “further assessments and analyzes are needed in some areas, taking into account the recommendations of the International Atomic Energy Agency mission”.

Source: bbj.hu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Paks II commissioning timeline uncertainty as Hungary’s nuclear replacement window tightens

Paks II schedule risk extends into 2035 Hungary’s Paks II nuclear expansion could see completion pushed to 2035, according to an internal construction timetable cited in a report. The same source indicates the project could be delayed until 2035, narrowing...

Hungary tenders 702 MVA grid capacity for new wind projects

Hungary has launched a tender for 702 MVA of grid connection capacity reserved for new wind projects. The allocation is intended to reopen access to grid capacity after a period in which wind development remained largely frozen while solar...

Hungary tenders 702 MVA grid capacity for new wind farm connections

Hungary has released 702 MVA of grid capacity for new wind projects and opened a tender for wind farm grid connections. The offering provides developers with 702 MVA of combined network capacity as the country seeks to restart wind...
Supported byVirtu Energy