Hungary: Paks II is preparing responses to OAH requests

Paks II, the project company to upgrade Hungary’s only commercial nuclear power plant, is speeding up the preparation of a response to a request from the National Atomic Energy Office (OAH) for further clarification on the licensing procedure for the two new units.

This news was confirmed by Alexander Merten, Deputy Director of ASE, Rosatom’s general contractor, in an interview published in the Hungarian business daily Vilaggazdasag.

“We will provide the requested information and answers as soon as possible,” Merten said.
The OAH had until the end of September to issue an implementation permit for the two blocks, but said in October that it had requested “further clarifications” for the procedure.

The office said the documentation submitted by Pax II was “very thorough in some respects”, but added that “further assessments and analyzes are needed in some areas, taking into account the recommendations of the International Atomic Energy Agency mission”.

Source: bbj.hu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Paks nuclear output cuts linked to low wholesale prices amid Hungary’s solar growth

Hungary’s Paks nuclear plant has reduced generation again after electricity could not be sold economically during low-price hours. The latest curtailment reflects how rising solar output is affecting the country’s baseload market profile. Paks curtailment during low-price hours Paks cut...

Hungary granted temporary EU delay on Serbia gas capacity bundling rules

Hungary has received temporary approval from the European Commission to postpone full implementation of EU gas-capacity rules at its border with Serbia until the 2027/2028 gas year. The derogation relates to requirements that cross-border pipeline capacity be offered as...

MVM begins foundations for 1 GW combined-cycle plant at Tiszaujvaros

Hungarian state-owned utility MVM has started foundation work on a new 1,000 MW combined-cycle gas-fired power plant at the former Tisza II site in Tiszaujvaros. The project is part of Hungary’s broader shift in generation needs as variable renewables...
Supported byVirtu Energy