ESM launches third phase of €46 million upgrade for six North Macedonia hydropower plants

North Macedonia’s state-owned utility ESM has started the third phase of a programme worth roughly €46 million to modernise six large hydropower plants. The initiative is designed to upgrade existing generating assets rather than build new capacity.

Capacity and generation targets

The works are expected to add 13.5 MW of capacity and increase annual generation by about 50 GWh. ESM estimates that the additional output could generate at least €5 million in annual revenue. Actual gains will depend on water availability, which remains a key constraint for hydropower generation.

Financing through KfW and EU support

The programme is financed by a €35 million KfW loan and a €10.7 million EU grant. The EU funding is provided through the Western Balkans Investment Framework.

Plants included in the modernisation programme

The upgrade covers Vrutok, Vrben, Raven, Tikveš, Špilje, and Globočica. Equipment replacement and plant upgrades are intended to improve reliability, reduce interruptions, and extend operating life.

The investment focuses on raising production from existing assets across the six sites. Output increases remain linked to hydrological conditions affecting generation volumes.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

North Macedonia aims for 38% renewables share by 2030

North Macedonia is targeting 38% renewable energy as a share of gross final energy consumption by 2030. The programme includes rapid solar expansion and additional hydropower generation, with parts of the plan reported to be ahead of the planned...

North Macedonia generation drops 22% in July as renewables rise

North Macedonia’s gross electricity generation declined 22.3% year on year to 460,035 MWh in July, even as hydro and wind output increased. The month’s generation mix included higher contributions from hydropower and wind compared with the same period a...

Envision selected for turbines in Stip wind project first phase, North Macedonia

Alcazar Energy Partners has reached financial close for the Stip wind project in North Macedonia. The first phase totals 131.25 MW and has moved toward construction after securing financing and selecting Envision Energy as turbine supplier. The project is...
Supported byVirtu Energy