ERS revises qualification rules for 60-MW Hrgud wind farm tender

Bosnian Serb power utility ERS has eased qualification requirements for the 60-MW Hrgud wind farm tender, following an appeal against the procurement documentation. The change widens the pool of potential bidders for the project’s €95 million engineering, procurement, construction and financing contract.

The revised conditions reduce both corporate-reference and staffing requirements. Under the updated rules, bidders must submit one reference covering the design and construction of comparable electricity infrastructure worth at least €25 million, excluding VAT, within the past five years. The earlier tender package required four separate references tied to a wind farm of at least 30 MW, a high-voltage substation, mountain roads and a 110-kV transmission line.

Updated experience and licensing requirements

ERS has also shortened the experience requirement for nine technical specialists from five years to two years. In addition, the utility simplified rules related to professional licences and construction methodology.

The procurement changes remove a requirement for bidders to produce their own technical and economic viability assessment demonstrating at least 160 GWh of annual net generation. ERS is expected to issue revised bid deadlines through a further amendment.

EPC+F scope and project build timeline

The contract is structured as EPC+F, meaning the successful contractor or consortium must arrange financing and deliver turbines, roads, substations and transmission infrastructure. The project is located in southern Bosnia and Herzegovina and is expected to include 10 turbines. The build is expected to take two years.

Hrgud’s measured wind speeds exceed eight metres per second. Expected annual generation is around 160 GWh, based on those measured conditions. The eased tender requirements may increase competition while placing additional responsibility on ERS to ensure bidders retain sufficient technical and financial capacity.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

ERS rejects immediate power tariff rise amid new renewables pipeline

Tariff position and price outlook Bosnian Serb power utility ERS has ruled out an immediate electricity-price increase, according to ERS General Director Luka Petrovic. The utility said it is relying on new wind, solar and hydropower projects to expand supply...

Energoinvest seeks Supreme Court review of gas transport tariff ruling in Republika Srpska

Energoinvest, a Sarajevo-based gas importer, plans to take a dispute over natural gas transportation charges to the Supreme Court of the Republic of Srpska. The company said it will challenge a ruling on how regulated network tariffs are applied,...

ERS unit seeks €11m capital boost for HE Bistrica hydropower project

Proposed recapitalisation and shareholder vote Hidroelektrane na Drini, part of Bosnia and Herzegovina’s Serb power utility ERS, is preparing another recapitalisation of the project company HE Bistrica. The latest proposal would convert around €11 million of short-term loans into permanent...
Supported byVirtu Energy