Supported byClarion Energy
HomeUncategorizedThermal power plant...

Thermal power plant

 

Although both 620MW units worked very well this year it is certain that they will not meet the anticipated annual production plan. The only reason for this is the extension of the capital overhaul of the unit B2 which was done this year- said Zoran Stojanovic, Director of TENT B.

The capital overhaul of the unit two was planned to last 100 days but due to the need and implementation of planned activities and those which were not planned originally it was extended for 21 days.

The planned 100 days should have been sufficient for the implementation of EU grant concerning the reconstruction of electrostatic precipitators. Experience with similar work on the unit A6 has shown that for such an activity it was necessary to provide longer overhaul for the unit B2.

Keeping this fact in mind it was decided to extend the overhaul to 120 days thus extending the scope of activities too. There was

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Southeast European electricity prices surge above €250/MWh as Serbia and Hungary face higher import costs

Electricity prices across Southeast Europe rose sharply for delivery on October 15, with Hungary and Serbia trading above €250/MWh as changing electricity balances in Romania, stronger regional demand and lower forecast wind generation increased pressure on cross-border markets. Hungary’s HUPX...

Enery begins Jezerce hybrid solar-battery build with €88/MWh municipal offtake

Vienna-based renewable energy group Enery has started construction of a hybrid solar and battery facility in Slovenia at the Jezerce project near Divača. The installation combines 7.68 MW of photovoltaic capacity with 12 MWh of electricity storage. Project location...

Alerion completes 32 MW Dănești solar plant in Romania’s Călărași county

Dănești project details and expected generation Italian renewable energy developer Alerion Clean Power has completed construction of the 32 MW Dănești solar power plant in Romania’s Călărași county. The project adds an operating asset to the company’s regional electricity generation...
Supported byVirtu Energy