Rețele Electrice România plans to invest about €23.5 million, including VAT, in the Cetate substation in Timișoara. The upgrade will replace ageing equipment and add capacity at a site serving more than 25,000 customers. The project is described as a substation expansion focused on strengthening the local electricity network.

Transformer and switchgear scope

A new 40 MVA transformer will be installed to supplement the substation’s existing 65 MVA capacity. The works also include 110 kV switchgear, along with lower-voltage equipment. A control-room upgrade is part of the scope and will be connected to the company’s remote management system.

Funding and project timeline

European funding of around €12.3 million, excluding VAT, will cover part of the investment. Completion is planned within 39 months of the financing agreement taking effect. The investment is intended to improve reliability for existing customers while providing additional capacity for changing demand on the local grid.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romanian 127 MW battery secures up to 44 million euros from EBRD

The Scornicesti battery will use non-recourse project finance with InvestEU risk support. Its merchant revenue model comes as Romania’s operational storage fleet expands and competition for market revenues grows.

Romania tops EU power costs at 46.9 units per 100 kWh

Romanian households faced the EU’s highest electricity costs on a purchasing-power basis in the first half of 2026. The country also recorded the bloc’s largest annual rise in household gas prices, at 9.3%.

Nuclearelectrica targets 6 November restart for 700 MW Romanian reactor

Nuclearelectrica expects to reconnect Cernavoda Unit 1 on 6 November 2026 after more than three months offline because low Danube levels disrupted cooling-water supplies. Unit 2 is expected to remain offline until river conditions support both reactors operating simultaneously.
Supported byVirtu Energy