Transelectrica commissions new 400 kV transformer station in Reșița, Romania

Romania’s transmission system operator Transelectrica has commissioned a new 400 kV transformer station in Reșița, in Caraș-Severin County. The upgrade also included modernization of an existing 220/110 kV substation at the same site. The commissioning follows completion of a major infrastructure project in the western part of the country.

The project is valued at €35.4 million excluding VAT and was financed from Transelectrica’s own resources. Construction was delivered by a consortium led by Siemens Energy, with Electrogrup and Retrasib as partners. The works were supported by subcontractors Energotech and Dacom Impex.

The scope covered the development of a new 400 kV facility and a full upgrade of existing transmission infrastructure at the Reșița location. This included changes to the substation configuration to accommodate the higher-voltage equipment commissioned by Transelectrica.

Reșița node role in Banat high-voltage corridor

The Reșița node supports power flows across western Romania’s electricity system as part of the Banat high-voltage transmission corridor. It is linked to connections involving Porțile de Fier, Reșița, Timișoara, and Arad. These elements are described as key for regional electricity transmission and system stability.

Transelectrica is also progressing related investments intended to complete a full 400 kV transmission corridor along the wider Porțile de Fier–Reșița–Timișoara–Săcălaz–Arad axis. The company states these projects are aimed at strengthening grid resilience and increasing capacity in its western network.

According to company management, more than €120 million in investments have already been implemented or are currently underway in western Romania. These initiatives target improved network reliability, expanded capacity for new electricity producers, and enhanced connections for large industrial consumers.

Cross-border projects with Serbia and regional interconnections

The expansion also supports cross-border transmission capability with Serbia, where exchange capacity has reached up to 1,000 MW. Transelectrica cites recent strategic projects including the 400 kV Reșița–Pancevo interconnection and the Porțile de Fier–Anina–Reșița line. Both are presented as critical for regional energy integration.

In parallel, Transelectrica is developing a new 400 kV corridor from Reșița toward Timișoara and Săcălaz, extending to Arad. The corridor is described as part of Romania’s western high-voltage energy ring and is supported through the Modernization Fund .

Investment pipeline and 2026 budget approval

The company has secured shareholder approval for a 2026 investment budget of around €184 million. Transelectrica said this represents a 30% year-on-year increase compared with the prior period. The approved plan is part of continued spending on transmission infrastructure upgrades.

The operator also indicated that it expects annual spending to rise to approximately €262 million in the coming years. This projection aligns with ongoing works across western Romania and related cross-border transmission projects .

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia targets early-2027 start for Romanian gas interconnector construction

Serbia expects construction of its gas interconnector with Romania to begin in early 2027, creating an import route intended to diversify supply and strengthen network resilience. Procurement for the Serbian section is expected to start shortly. Most technical and...

Lukoil appoints Eugene Maniakhine to oversee Petrotel refinery restructuring

Lukoil has appointed Eugene Maniakhine to oversee the restructuring of its Petrotel refinery in Romania. The facility entered insolvency proceedings in August 2026 after remaining offline since the previous year. The restructuring process is being handled under Romanian insolvency...

Romania targets Neptun Deep first gas in H1 2027 as execution advances

Romania has narrowed the Neptun Deep first-gas window to the first half of 2027, from a broader timetable previously associated with the €4 billion Black Sea development. The project is expected to bring about 8 bcm/year of production closer...
Supported byVirtu Energy