EMS begins Bajina Bašta 220 kV to 400 kV upgrade for Trans-Balkan Corridor

Serbian transmission system operator EMS has started upgrading the Bajina Bašta substation from 220 kV to 400 kV, supporting the western segment of the Trans-Balkan Corridor. The project covers the current corridor section valued at around €115 million. The works are underway as part of broader grid reinforcement in Serbia.

Bajina Bašta switchyard and transformer scope

At Bajina Bašta, EMS is building a new 400 kV switchyard and installing two 400 MVA transformers. The upgrade is being implemented alongside grid expansion measures in the surrounding transmission network. These parallel works are designed to align substation capacity with associated line and connection developments.

Obrenovac line and bay additions

The Bajina Bašta works are being carried out together with a double-circuit 2×400 kV line from Obrenovac. EMS is also adding two additional bays at the Obrenovac substation. This combination of substation equipment, line capacity and bay additions forms part of the same reinforcement package for the corridor.

The upgrade is intended to provide network capacity for the planned Bistrica pumped-storage plant. The corridor’s third section is scheduled for 2028, while a further section toward Bosnia and Herzegovina and Montenegro is planned for 2029. Once completed, those links are expected to increase capacity available for cross-border electricity flows.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia power prices rise as regional markets retreat from Tuesday’s spike

Serbia’s day-ahead electricity price rose by €18.2/MWh to €195.99/MWh for Wednesday delivery, moving in the opposite direction to sharp declines across most neighbouring markets and narrowing the gap with Hungary to just €2.99/MWh. Hungary’s HUPX benchmark fell by €34.9/MWh to...

Fortis and Inelso to build 30 MW solar with battery storage in Vojvodina

Fortis Energy and Inelso Energy Systems plan to invest about €25.5 million in a 30 MW solar project with battery storage in Serbia’s Vojvodina region. The development is described as ready to build. The project is expected to proceed...

Serbia: Belgrade launches geothermal drilling programme for district heating

Belgrade district-heating utility Beogradske Elektrane has launched a tender for exploratory geothermal drilling at its New Belgrade and Miljakovac heating plants, marking a move from geological assessment to on-site testing of potential geothermal resources. The two locations were identified as...
Supported byVirtu Energy