EMS begins Bajina Bašta 220 kV to 400 kV upgrade for Trans-Balkan Corridor

Serbian transmission system operator EMS has started upgrading the Bajina Bašta substation from 220 kV to 400 kV, supporting the western segment of the Trans-Balkan Corridor. The project covers the current corridor section valued at around €115 million. The works are underway as part of broader grid reinforcement in Serbia.

Bajina Bašta switchyard and transformer scope

At Bajina Bašta, EMS is building a new 400 kV switchyard and installing two 400 MVA transformers. The upgrade is being implemented alongside grid expansion measures in the surrounding transmission network. These parallel works are designed to align substation capacity with associated line and connection developments.

Obrenovac line and bay additions

The Bajina Bašta works are being carried out together with a double-circuit 2×400 kV line from Obrenovac. EMS is also adding two additional bays at the Obrenovac substation. This combination of substation equipment, line capacity and bay additions forms part of the same reinforcement package for the corridor.

The upgrade is intended to provide network capacity for the planned Bistrica pumped-storage plant. The corridor’s third section is scheduled for 2028, while a further section toward Bosnia and Herzegovina and Montenegro is planned for 2029. Once completed, those links are expected to increase capacity available for cross-border electricity flows.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

NIS operating window extends to 11 December 2026 amid uncertainty

Serbia’s crude supply chain remains dependent on temporary sanctions authorisations, with the operating window for NIS and corresponding JANAF activities extended to 11 December 2026. Uncertainty persists over MOL’s proposed acquisition of the Russian majority stake in NIS.

Serbia builds 1.5 bcm/year gas link as costs shape diversification

Serbia is expanding gas-supply options with a 1.5 bcm per year interconnector to North Macedonia under construction. The commercial value will depend on delivered costs, route reliability, storage and the expense of new infrastructure.

Romanian offshore gas growth puts export capacity in focus

Romania’s expected offshore gas production growth could leave additional supply discounted domestically unless cross-border capacity can move it to higher-priced markets. Capacity constraints could also increase the value of transmission upgrades and create recurring price spreads with Hungary and Serbia.
Supported byVirtu Energy