Slovenia: New 400 kV switchyard testing in Cirkovce

Slovenian electricity transmission system operator ELES launched reconstruction and upgrade of Cirkovce substation within the framework of constructing the new double-circuit 400 kV overhead line Cirkovce-Pince, which will connect the Slovenian electricity network with the Hungarian one.

ELES started the functional testing of the new 400 kV switchyard in the Cirkovce substation, which was planned along with the 2×400 kV Cirkovce-Pince overhead line. Four new 400 kV transmission fields have become active in Cirkovce substation, two of which go towards the city of Maribor, one towards NPP Krsko and one towards the village of Podlog. Thus, Cirkovce became the largest switchyard in the country.

The construction of the first electricity interconnection between Slovenia and Hungary started in October 2020. The 80 kilometers long power line between Cirkovce near Ptuj and Pince on the border with Hungary will establish a link between the Hungarian and Slovenian national grids and consequently Croatia. The 150 million euros project has been in the making for almost two decades, mainly due to lengthy zoning procedures. ELES expects for the 2×400 kV power line to be linked internationally by the end of 2021 with the project to be fully completed with final details by the end of 2022.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia appoints GEN leadership ahead of Krško 2 nuclear project decisions

New executives at GEN energija and GEN-I Slovenia has appointed new leadership at state-owned GEN energija and electricity supplier and trader GEN-I, changing management at two of the country’s key energy companies as decisions on the proposed Krško 2 nuclear...

Slovenian household electricity and gas prices rise in Q2 2026

Slovenian household electricity and natural gas prices increased in the second quarter of 2026. Households paid an average €0.215/kWh for electricity and €0.087/kWh for natural gas. The changes were measured against the first quarter. Quarterly changes for household tariffs Electricity prices...

Slovenia appoints new GEN energija and GEN-I leaders for Krško 2 and Mokrice

Slovenia has appointed new leadership at state energy group GEN energija and electricity trader GEN-I, following a change in the country’s government. Andrej Vizjak, incoming chief executive at GEN energija, said work on the planned Krško 2 nuclear project...
Supported byVirtu Energy