HPP Bradisor is currently operating below full capacity (at 40-50 MW) due to risks imposed by the wear of its equipment. The refurbishment of the turbines and adjacent transformer station should be completed within 36 months.

Romanian electricity producer Hidroelectrica is planning to propose to its shareholders the project for the reconstruction of 115 MW HPP Bradisor with expected cost of some 35 million euros.

Hidroelectrica is the largest electricity producer in Romania with 6,444 MW of installed capacity in 204 hydropower plants. Its largest shareholder is the Romanian state with 80 % stake, while the remaining 20 % is held by private investment fund Fondul Proprietatea.

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...