Romania, HPP Raul Mare Rezetat could never produce electricity at the designed capacity

Although it is in operation since 1986, hydropower plant Raul Mare Rezetat could never produce electricity at the designed capacity. From the very beginning, the two units of local production, with design and execution defects, could only be used at a maximum capacity of 100 MW each.

However, 45 years after the commissioning, the plant’s reservoir – Gura Apelor lake was filled to the projected parameters last week. Together with the launched tender for the plant’s reconstruction, HPP Raul Mare Retezat could finally be operating at full capacity in 4 to 5 years.

Launched in April 2021, the tender is now in the stage of technical analysis of the only offer that met the preliminary criteria. The offer was submitted by a consortium led by Voith Hydro. Once the technical conditions are established, at the earliest in the spring of 2022, the financial framework will be finalized, within a budget of almost 77 million euros. The investment will then be prepared in about 12 months, and the actual works will take another 3 years.

The reconstruction will include the manufacture, installation and commissioning of the hydraulic turbine, electric generators, SCADA automation systems, as well as other hydromechanical equipment. Following the reconstruction, the installed capacity of the hydropower plant will be increases from a maximum of 200 MW to 335 MW, a gain of about 67 %, equivalent to the installed capacity of the entire chain of small hydropower plants downstream from HPP Raul Mare Retezat.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Enercon to deliver 7-MW turbines for Qair’s Cobadin I wind farm in Romania

Enercon will supply its E-175 EP5 E2 turbine platform for Qair’s Cobadin I wind farm in Romania. The project is described as a 50-MW development under the first phase of the Cobadin complex. The deployment marks the first time...

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...
Supported byVirtu Energy