Romania, Fees for electricity distribution and transmission services will not be increased from 1 January

According to a draft order of the National Regulatory Authority for Energy (ANRE), the fees for electricity distribution and transmission services will not be increased from 1 January, as it was intended, but from 1 April 2022.

ANRE pointed out that, given that the consumer support mechanism, which includes price caps, is in place during the winter, the network fees, which are included in final electricity price, will be maintained during this period.

The draft order states that, considering the provisions of the Law according to which for the period between 1 November 2021 and 31 March 2022, for certain categories of final customers, the capped final price is set at a maximum of 0.2 euros/kWh and a reference price of 0.14 euros/ kWh which includes fees for electricity transmission and distribution services, it is proposed to maintain in force the current fees until 31 March 2022.

At the same time, it is provided that the income differences of the network operators resulting in the abovementioned period are recovered according to the provisions of the methodologies in force.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania extends 25% diesel excise reduction through 15 October

Romania has extended its 25% excise-duty reduction on standard diesel through 15 October. The measure is set to continue into October after being previously applied during September. The extension keeps the tax relief in place while higher international prices...

Transelectrica launches €90.4m digital upgrade for Alba Iulia 220/110/20 kV substation

Romanian transmission operator Transelectrica has launched a €90.4 million upgrade of its Alba Iulia 220/110/20 kV substation, excluding VAT. The project is intended as a pilot for broader digitalisation of the national grid. The scope links substation equipment with...

Rezolv financing up to €561 million for 1.3 GW Dama Solar in Romania

Rezolv Energy has secured financing of up to €561 million for its 1.3 GW Dama Solar development in western Romania, enabling the project to move into construction ahead of planned commercial operation in the second half of 2028. The...
Supported byVirtu Energy