HSE trial operation expands Prapretno solar complex with 7-MW battery storage

HSE begins trial operation at Prapretno 2 and 3

Slovenian state-owned utility HSE has started trial operation of the Prapretno 2 and Prapretno 3 solar plants. The start of commissioning expands the site into Slovenia’s largest operating photovoltaic complex. The project also includes battery storage designed to manage variable generation.

The completed installation combines 9.8 MW of solar capacity with more than 17,900 modules. HSE has installed a 7-MW/14-MWh battery at the site. The battery enables electricity shifting between periods and provides additional grid support.

Site redevelopment and EU Just Transition Fund co-financing

Prapretno 2 and Prapretno 3 were developed on land previously used for depositing ash and slag from a coal-fired power plant. HSE said the development is Slovenia’s first renewable project to receive co-financing from the EU Just Transition Fund. The new phases are part of a broader redevelopment of former coal regions.

HSE stated that using degraded industrial land can avoid land-use conflicts associated with some greenfield renewable projects. The original Prapretno solar plant, with a capacity of 3 MW, was commissioned more than four years ago. At the time, it was Slovenia’s largest photovoltaic facility.

Hybrid generation and storage configuration

The addition of the two new phases changes the site into a hybrid generation and storage complex. HSE described the investment as an expansion that pairs new solar generation with flexibility rather than operating it as a standalone asset. The battery capacity is relatively small in comparison with the overall solar buildout, according to the project design approach.

The trial operation of Prapretno 2 and Prapretno 3 therefore brings both solar output management and grid support elements under one configuration at the expanded site.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EIB open to financing Slovenia nuclear expansion at Krsko

The European Investment Bank is prepared to consider financing nuclear investments in Slovenia, including a possible second reactor at the Krsko power plant. The lender said it is moving toward a more technology-neutral approach to low-carbon energy. Any support...

HSE construction permit for 1.38-MW solar and 1.25-MW/5-MWh battery in Zagorje ob Savi

Slovenian power utility HSE has secured a construction permit for a solar and battery project at the former Kamnolom Zagorje municipal landfill in Zagorje ob Savi. The development is linked to plans for site redevelopment in 2027. Planned generation,...

Slovenia appoints GEN leadership ahead of Krško 2 nuclear project decisions

New executives at GEN energija and GEN-I Slovenia has appointed new leadership at state-owned GEN energija and electricity supplier and trader GEN-I, changing management at two of the country’s key energy companies as decisions on the proposed Krško 2 nuclear...
Supported byVirtu Energy