Greece, Seeking to secure additional funds for the replacement of overhead power lines with underground infrastructure

The Greek Ministry of Energy, due to the extent of damage taken by recent fires, as well as heavy snowfall during winter, has taken measures to clear the way of any possible bureaucratic delays and is also seeking to secure additional funds for the replacement of overhead power lines with underground infrastructure.

This includes measures, such as facilitating power line undergrounding by operators through forest land without them having to wait for approval from forestry officials. As a result, electricity transmission and distribution operators ADMIE and DEDDIE can now proceed with power line undergrounding projects without delay or cancellation risks. This applies for both new power line networks and replacement of older ones.

EU Recovery and Resilience Facility will provide a total of 187 million euros for power line projects. However, given the average cost of power line network undergrounding of some 85,000 euros per kilometer, the funds will be enough for just 2,200 kilometers, which is just a tiny fraction of the country’s existing overhead power lines.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy