The European Union is supporting expansions at three gas storage facilities in Romania and Bulgaria. The upgrades are designed to increase both reserves and delivery capacity to help regional markets manage supply disruptions and winter demand. Funding through the Connecting Europe Facility will cover 35–50% of eligible project costs.

Bilciurești expansion targets higher withdrawal and working gas

At Romania’s Bilciurești facility, daily withdrawal capacity is set to rise to 20 million cubic metres from 14 million. Working gas capacity will increase by 108 million cubic metres, or about 9%. The changes focus on raising the amount of gas that can be withdrawn during periods of higher demand.

Depomureș phase increases working capacity and daily rates

The first phase of the Depomureș expansion will add 100 million cubic metres. This will bring working capacity to 400 million cubic metres. Injection and withdrawal rates are expected to increase by around 75% to 3.5 million cubic metres a day.

Chiren expansion in Bulgaria raises injection and withdrawal capability

Bulgaria’s Chiren facility is being expanded towards 1 billion cubic metres of storage. Injection and withdrawal capacity is expected to reach 8–10 million cubic metres a day. The projects address constraints related not only to storage volume but also to how quickly operators can release gas when demand rises.

Faster withdrawals could strengthen supply flexibility across neighbouring markets, provided sufficient cross-border transport capacity is available.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Transelectrica launches €90.4m digital upgrade for Alba Iulia 220/110/20 kV substation

Romanian transmission operator Transelectrica has launched a €90.4 million upgrade of its Alba Iulia 220/110/20 kV substation, excluding VAT. The project is intended as a pilot for broader digitalisation of the national grid. The scope links substation equipment with...

Rezolv financing up to €561 million for 1.3 GW Dama Solar in Romania

Rezolv Energy has secured financing of up to €561 million for its 1.3 GW Dama Solar development in western Romania, enabling the project to move into construction ahead of planned commercial operation in the second half of 2028. The...

Romania’s Romgaz rejects 20-year US LNG contract amid projected losses

Romanian gas producer Romgaz has rejected a proposed 20-year US LNG contract. The company said its assessment pointed to potential annual losses ranging from €50 million to €310 million, depending on US and European gas prices. The offer was put...
Supported byVirtu Energy