In a significant move to bolster its energy infrastructure, Greece has initiated a fast-track evaluation process for standalone battery storage projects under a 4.7 GW market-based tender. This initiative aims to modernize the energy sector and enhance grid flexibility, reflecting the country’s commitment to energy transition.

A newly formed committee is actively reviewing project proposals to expedite the identification of projects primed for implementation. This committee includes representatives from ADMIE, the Independent Power Transmission Operator, and DEDDIE, the Hellenic Electricity Distribution Network Operator, ensuring effective coordination across both transmission and distribution networks, which is essential for seamless project integration.

The initial phase of this process will concentrate on approximately 2 GW of capacity, with preliminary rankings anticipated by June. Of this capacity, around 900 MW is designated for connection to the distribution network, while approximately 1.1 GW will be connected to the transmission system, demonstrating a balanced allocation across various grid levels.

The evaluation process will align submissions from the Ministry of Environment and Energy with those from network operators. Eligible projects will be prioritized based on established tender criteria after confirming compliance with formal requirements. On the distribution side, DEDDIE will evaluate hundreds of proposals exceeding 2 GW in total capacity, while ADMIE will focus on a subset of transmission projects categorized by technical specifications, indicating strong competition and significant investor interest in this sector.

As the first ranking lists are set to be finalized in the coming weeks, this development is expected to facilitate grid connection approvals for initial projects. The remaining pipeline of around 2.7 GW will undergo assessment at a later stage once additional technical parameters are established, ensuring a structured and phased rollout of battery storage capacity across Greece.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Faria Renewables acquires 23.1 MW Greek wind farm

Greek developer Faria Renewables has completed the purchase of a 23.1 MW wind farm in Boeotia from EDP Renewables. The acquisition adds an operating renewable asset to Faria’s portfolio. It is the first of two wind projects included in...

Greece adds 2.7 GW of renewables as solar curtailment grows

Greece connected around 2.7 GW of new wind projects and solar capacity in the first ten months of 2026, bringing its renewable portfolio to roughly 19 GW. About 2.1 GW of the additions was solar and 600 MW was...

Crete-Cyprus Interconnector Advances to Seabed Surveys

Survey teams are preparing to examine the seabed along the proposed submarine cable route for the Great Sea Interconnector between Crete, Greece, and Cyprus. The French research vessel Abeille Marengo has arrived in Crete and is waiting for authorisation...