Bosnia and Herzegovina: EPBiH to build 60 MW solar power plants

 

State-owned power utility EPBiH will build eight solar power plants near Zivinice, a project worth some 43.5 million euros.  Solar power plants should be operational by the end of 2024.

Solar power plants will be built at depleted open pit mines at Djurdjevik and Basigovci. Preliminary designs are already completed. The company now prepares to submit documentation for the issuance of an urban planning permit.

The total installed capacity of the eight power plants will be around 60 MW. Produced electricity will be consumed locally. The project is financially supported by the European Bank for Reconstruction and Development (EBRD).

EPBiH plans to build solar power plants on the ash deposits of several of its coalmines, including Kreka, Breza and Kakanj, and its coal-fired TPP Tuzla by 2030.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPBiH coal shortages raise risk of further electricity tariff pressure in 2026-2027

EPBiH, the state-owned power utility in Bosnia and Herzegovina, faces renewed electricity-price pressure as coal supply problems contribute to losses. The company could see pressure for another electricity-price increase by late 2026 or early 2027, according to the conditions...

EBRD considers senior loan for ENNA’s Mihailesti solar-plus-storage in Romania

The European Bank for Reconstruction and Development is reviewing a potential senior loan for ENNA Group’s Mihailesti solar and storage project in southern Romania. The bank’s financing decision is expected by early November. The proposed loan amount has not...

EPBiH tenders main design work for 16 MW Janjići hydropower after court ruling

Bosnia and Herzegovina’s state-owned EPBiH has opened a new tender for the preparation of the main design of the 16 MW Janjići hydropower plant on the Bosna River. The procurement follows a legal setback related to the project’s environmental...