EPBiH tenders main design work for 16 MW Janjići hydropower after court ruling

Bosnia and Herzegovina’s state-owned EPBiH has opened a new tender for the preparation of the main design of the 16 MW Janjići hydropower plant on the Bosna River. The procurement follows a legal setback related to the project’s environmental permitting.

The contract is estimated at around €800,000, with the lowest offered price set as the main selection criterion. Bids must be submitted by 16 October.

Environmental permit annulment and legal findings

The project remains subject to environmental and legal complexity. In April 2025, the Cantonal Court in Sarajevo annulled a decision by the Federal Ministry of Environment and Tourism that had rejected an application to renew the project’s environmental permit.

The court determined that the ministry misapplied the law, breached procedures, and failed to respect obligations under the Aarhus Convention. The ruling overturned the ministry’s 2021 decision concerning the proposed 16 MW facility.

New tender timeline for main design preparation

The new design procurement advances the technical process, while permitting continues to represent an execution risk. The tender was launched on 2 September 2025.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

ERS unit seeks €11m capital boost for HE Bistrica hydropower project

Proposed recapitalisation and shareholder vote Hidroelektrane na Drini, part of Bosnia and Herzegovina’s Serb power utility ERS, is preparing another recapitalisation of the project company HE Bistrica. The latest proposal would convert around €11 million of short-term loans into permanent...

Hrgud 60-MW wind farm tender halted by complaint in Bosnia and Herzegovina

A formal complaint has stopped the latest procurement for the 60-MW Hrgud wind farm in Bosnia and Herzegovina, extending delays for one of Republika Srpska’s longest-running renewable-energy projects. The procurement cannot proceed on its original timetable until the objection...

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...
Supported byVirtu Energy