Bosnia and Herzegovina’s planned 100-MW wind energy project near Tomislavgrad has cleared an environmental screening stage, with authorities deciding that a full environmental impact assessment is not required.
The Federal Ministry of Environment and Tourism issued the decision for the Gradina project, which is associated with Lager Group. Plans envisage 17 turbines on the Grabovica plateau and in the surrounding Miden area.
If built, Gradina would be among Bosnia and Herzegovina’s larger wind projects. Preliminary estimates for comparable developments suggest potential investment of €150 million to €200 million; this is not a confirmed budget from the developer.
Infrastructure and turbine specifications
The project plans include a 220/33-kV substation and more than 22 kilometres of internal electrical cabling. Around 28 kilometres of roads are also envisaged, combining new access routes with upgrades to existing roads.
Depending on the final equipment selection, turbine towers are expected to stand between 130 and 150 metres tall. Rotor diameters could reach around 200 metres, with blades measuring about 100 metres.
Further approvals remain necessary
The environmental screening decision is not a construction permit, and the project still needs other regulatory approvals before work can begin. By removing one potentially lengthy permitting step, the decision allows the developer to continue preparations under the remaining approval procedures.
Gradina would add to a growing pipeline of large wind developments in Bosnia and Herzegovina. Strong wind resources have attracted developers, while permitting, grid access and financing remain important constraints.