Serbia’s Kovačica wind complex is set to reach 200 MW of installed capacity after adding the Pupin wind farm. The 95.5 MW Pupin development is backed by a €140 million investment supported by international lenders and renewable energy developers. The addition is expected to bring the overall project capacity close to doubling the existing Kovačica site.

The original Kovačica project entered commercial operation in 2019 with 104.5 MW. With the Pupin expansion, the combined development is designed to increase turbine numbers from 38 to 54. The new Pupin phase includes 16 Nordex wind turbines.

Pupin generation profile and household-equivalent output

Pupin is expected to generate approximately 220 GWh annually. The projected output is described as equivalent to the electricity requirements of more than 40,000 households. The figures relate specifically to generation from the Pupin wind farm within the Kovačica-Pupin complex.

The project is being developed by Enlight Renewable Energy, working in partnership with Serbian developer New Energy Solutions. Enlight and New Energy Solutions previously collaborated on the original Kovačica wind farm. That earlier cooperation is cited as enabling the expansion to build on an established development partnership.

Lenders, turbine supplier and construction consortium

Financing for the new investment was arranged with support from the European Bank for Reconstruction and Development (EBRD), along with Erste Group and Erste Bank. The involvement of international financial institutions and commercial banks is presented as reflecting ongoing lender interest in Serbian renewables projects. The projects are described as having defined technical specifications, experienced developers and established grid infrastructure.

Turbine supply for Pupin is provided by Nordex. Construction works were entrusted to a consortium of Serbian contractors led by WD Concord West and Elektrozapad. The project is also described as highlighting the role of domestic engineering and construction companies in delivering larger renewable generation investments.

System impact, dispatch considerations and market factors

The additional wind capacity is expected to increase domestic renewable generation in Serbia. It may also reduce reliance on imported electricity during periods of favourable wind conditions. The commercial contribution of the project, however, depends on more than annual output alone.

The performance assessment cited includes generation forecasting, balancing arrangements, grid availability and prices achieved during actual production hours. The expansion is taking place as Serbia continues managing how renewable growth aligns with transmission infrastructure and the need for dispatchable electricity supply. These factors shape how wind generation translates into market outcomes.

The Kovačica-Pupin complex concentrates wind capacity at a single development location. The longer-term economic value is linked to reliable production, operational efficiency and the ability to market wind-generated electricity in a regional power system described as increasingly volatile.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia secures environmental approval for 113-kilometre Hungary-Novi Sad crude pipeline

Environmental impact assessment clears for Transnafta project Serbia has received environmental approval for a proposed 113-kilometre crude oil pipeline linking Hungary with Novi Sad. The Serbian Ministry of Environmental Protection approved the project’s environmental impact assessment after a request from...

Serbia power prices plunge 25% as nuclear shortages keep Romanian and Bulgarian markets elevated

Serbia’s wholesale electricity price fell by almost 25% for Saturday delivery as weaker weekend demand eased pressure on the market. However, Romania, Bulgaria and Montenegro remained above €230/MWh, highlighting a growing divergence between Serbia and other Southeast European markets...

Baranda Energetski Park advances 317 MW solar with 31.7 MW battery near Opovo

Baranda Energetski Park is developing a proposed 317 MW solar project near Opovo in Serbia, alongside a 31.7 MW/126.8 MWh battery system. The developer says sensitive land conditions will influence the project’s development schedule. The proposal combines solar generation...
Supported byVirtu Energy