Krško nuclear plant generates 487,438 MWh in September 2026, misses target

The Krško nuclear power plant, jointly owned by Slovenia and Croatia, produced 487,438 MWh of net electricity in September 2026. Output was 1.53% below the plant’s monthly production target for the month. The reported shortfall followed a plan to generate 495,000 MWh, implying an output gap of approximately 7,562 MWh.

Despite missing the September target, generation rose year on year. September output increased by around 8.5% compared with 449,426 MWh recorded in September 2025. In the same month last year, the plant also exceeded its planned output of 446,000 MWh by 0.77%.

Operating report shows full availability and capacity factors

The latest operating report stated that Krško remained within its technical operating specifications. It also said all safety systems were available during the reporting period. Both the availability factor and capacity factor were reported at 100%.

No technical problems were identified in the report for the period covered by the September generation figures. The data suggests that the production shortfall was not accompanied by a reported operational failure. However, the available information does not specify the precise cause of the difference between planned and actual electricity output.

Role in Slovenia and Croatia power systems

Krško is described as providing low-carbon baseload generation for both Slovenia and Croatia. Its output is intended to reduce reliance on fossil-fuelled production and imported power in regional electricity markets. The plant’s generation is particularly relevant when wind and solar output are reduced or when electricity demand increases.

Predictable nuclear production supports supply planning in both countries. It also contributes to managing wholesale electricity procurement requirements. The September results highlight how performance against a monthly generation plan can differ from broader operational reliability.

Although Krško fell modestly short of its September target, generation remained substantially above the corresponding month of 2025. No reported technical or safety-related interruption was associated with the month’s outcome. The operating result indicates a limited production variance rather than evidence of a material deterioration in plant reliability.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia advances Mokrice hydropower project towards construction

Slovenia’s government has found that the public benefits of the Mokrice hydropower project outweigh its environmental impact, clearing another major regulatory hurdle for the long-delayed development. Led by Hidroelektrarne na spodnji Savi, the project could move towards construction in...

Slovenia opens electricity market to Nord Pool and CROPEX, intensifying exchange competition

Slovenia has opened its wholesale electricity market to competing exchange operators, giving Nord Pool and Croatia’s CROPEX the opportunity to challenge incumbent BSP SouthPool. The move could reshape trading services, market-access costs and operational risk management across Southeast Europe. The...

CROPEX expands into Slovenia’s day-ahead electricity market

Croatian electricity exchange CROPEX has expanded its operations into Slovenia’s day-ahead electricity market, marking a significant step in its regional growth as competition intensifies across Europe’s increasingly integrated power market. CROPEX began operations in Slovenia on October 21 under the...
Supported byVirtu Energy