The Krško nuclear power plant, jointly owned by Slovenia and Croatia, produced 487,438 MWh of net electricity in September 2026. Output was 1.53% below the plant’s monthly production target for the month. The reported shortfall followed a plan to generate 495,000 MWh, implying an output gap of approximately 7,562 MWh.

Despite missing the September target, generation rose year on year. September output increased by around 8.5% compared with 449,426 MWh recorded in September 2025. In the same month last year, the plant also exceeded its planned output of 446,000 MWh by 0.77%.

Operating report shows full availability and capacity factors

The latest operating report stated that Krško remained within its technical operating specifications. It also said all safety systems were available during the reporting period. Both the availability factor and capacity factor were reported at 100%.

No technical problems were identified in the report for the period covered by the September generation figures. The data suggests that the production shortfall was not accompanied by a reported operational failure. However, the available information does not specify the precise cause of the difference between planned and actual electricity output.

Role in Slovenia and Croatia power systems

Krško is described as providing low-carbon baseload generation for both Slovenia and Croatia. Its output is intended to reduce reliance on fossil-fuelled production and imported power in regional electricity markets. The plant’s generation is particularly relevant when wind and solar output are reduced or when electricity demand increases.

Predictable nuclear production supports supply planning in both countries. It also contributes to managing wholesale electricity procurement requirements. The September results highlight how performance against a monthly generation plan can differ from broader operational reliability.

Although Krško fell modestly short of its September target, generation remained substantially above the corresponding month of 2025. No reported technical or safety-related interruption was associated with the month’s outcome. The operating result indicates a limited production variance rather than evidence of a material deterioration in plant reliability.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Enery begins Jezerce hybrid solar-battery build with €88/MWh municipal offtake

Vienna-based renewable energy group Enery has started construction of a hybrid solar and battery facility in Slovenia at the Jezerce project near Divača. The installation combines 7.68 MW of photovoltaic capacity with 12 MWh of electricity storage. Project location...

Slovenia’s industrial power-sharing model delivers measurable savings as market scales

Slovenia’s electricity-sharing market is beginning to deliver measurable savings for industrial consumers, strengthening the case for an emerging energy-service model focused on allocating existing renewable generation more efficiently rather than building additional generation assets. Slovenian energy technology company SunContract said...

Slovenia extends application deadline for €68.97m electricity distribution investment

Slovenia has extended the application deadline for its €68.97 million electricity distribution investment programme to 30 November 2026, giving applicants additional time to complete technical documentation. The previous deadline was 31 October. The funding allocation remains unchanged. Funding split and...
Supported byVirtu Energy