Serbia recorded an 8.38% increase in electricity consumption, reaching 699.41 GWh in the week ended November 1, placing it among the markets with the strongest demand growth in Southeast Europe. Higher consumption, combined with a significant decline in wind and solar generation, increased pressure on domestic power plants and electricity imports, according to data from the Institute of Energy for South-East Europe (IENE).
Combined wind and solar generation in Serbia fell by 29.4% week on week, while thermal electricity production increased by 9.06%. Net electricity imports also rose, recording a 3.71% increase. At the same time, the country’s average day-ahead electricity price reached €286.55/MWh, just €0.71/MWh below Romania, which recorded the highest regional average.
Considerable price fluctuations were also observed throughout the week. The SEEPEX daily average reached €330.04/MWh on October 29, before falling to €261.47/MWh by November 1. This volatility highlights the challenges of relying on monthly or annual average prices when evaluating electricity procurement costs, particularly for industrial consumers with significant exposure to day-ahead market movements.
Although the available generation and trade figures do not establish whether higher imports resulted from power plant outages, commercial optimisation or other operational factors, the overall trend points to increasing pressure on Serbia’s electricity system. Rising consumption, weaker variable renewable generation and greater thermal output coincided with elevated wholesale market prices.
For industrial consumers, electricity suppliers and lenders, these developments reinforce the need for closer assessment of hourly consumption and procurement profiles, physical hedging arrangements, collateral requirements and contracted electricity supply. As the winter season approaches, managing exposure to short-term price volatility and supply availability will become increasingly important for market participants, making headline wholesale price averages only one part of the overall risk assessment.