EPBiH tenders main design for 16 MW Janjici hydropower plant on Bosna River

Bosnia and Herzegovina’s state-owned utility EPBiH has launched a tender for the main design of the proposed 16 MW Janjici hydropower plant on the Bosna River. The contract value is estimated at €800,000. The lowest price is set as the main criterion for selecting the winning bid. Offers are due by 16 October.

Environmental permit dispute reaches Cantonal Court ruling

The Janjici project has been tied to extensive legal proceedings related to its environmental permit. In April 2025, the Cantonal Court in Sarajevo overturned a decision by the Federal Ministry of Environment and Tourism. That earlier decision had rejected the renewal of the plant’s environmental permit.

Court cites legislation, procedure and Aarhus obligations

The court found that the Ministry misapplied relevant legislation and breached procedural requirements. It also ruled that the Ministry failed to meet obligations under the Aarhus Convention. The case was brought by the Aarhus Resource Center in Bosnia and Herzegovina, and the ruling effectively overturned the Ministry’s 2021 decision refusing renewal of the environmental permit.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

UK sanctions put Republika Srpska oil firms at financial risk

In Bosnia and Herzegovina, measures imposed by the United Kingdom against Russian state-owned oil producer Zarubezhneft could disrupt banking and cross-border transactions for Republika Srpska petroleum companies, including Nestro Petrol and Optima Group. The restrictions also cover entities directly...

Bosnia and Herzegovina launches €32.3 million Bistrica grid tender

The Bistrica hydropower development in Bosnia and Herzegovina’s Republic of Srpska has opened a €32.3 million tender for infrastructure to connect its three planned plants to the transmission grid. The contract includes the Miljevina substation and lines linking the...

Republic of Srpska Plans Tighter Solar Rules After 3,064 Hectares Reclassified

Authorities in Bosnia and Herzegovina’s Republic of Srpska are preparing tighter restrictions on photovoltaic developments on agricultural land. The rapid expansion of solar power has contributed to the conversion of thousands of hectares of farmland. The entity’s agriculture ministry...
Supported byVirtu Energy