Supported byClarion Energy
HomeSEE Energy NewsEBRD considers senior...

EBRD considers senior loan for ENNA’s Mihailesti solar-plus-storage in Romania

The European Bank for Reconstruction and Development is reviewing a potential senior loan for ENNA Group’s Mihailesti solar and storage project in southern Romania. The bank’s financing decision is expected by early November. The proposed loan amount has not been disclosed.

Project capacity and battery duration

The development combines 87.5 MW of solar capacity with a 70 MW/140 MWh battery system. At its rated power, the storage is equivalent to two hours of discharge. Neither the total investment cost nor other financial terms have been made public.

Location, output and emissions impact

The project is located in Giurgiu county. Once operational, it is expected to generate approximately 115 GWh annually. It is also forecast to avoid an estimated 47,000 tonnes of CO₂ emissions per year.

Contractor selection and ownership structure

ENEVO Group has been selected as the engineering, procurement and construction contractor. ENNA acquired the development in 2025 from Vienna-based Kraftfeld Solar. The asset is held through PVP Cepheus, which is owned by ENNA Solar and ultimately controlled by Croatia-based ENNA Group.

Storage role in market timing

The project pairs solar generation with storage to provide flexibility over when electricity reaches the market. The financing decision is described as a key step toward delivery. The eventual revenue structure is expected to determine how much value the battery captures from shifting output between trading periods.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania’s Cernavoda outage raises winter electricity cost exposure

Romania is facing continued pressure on electricity supply costs as both Cernavoda nuclear units remain offline without a firm restart timetable. With the nuclear capacity unavailable, the system is relying more heavily on other generation sources through the winter...

Romania seeks to extend emergency power controls as supply risks persist

Romania is seeking to extend its emergency electricity-market powers through October 31, maintaining the option to restrict exports or limit industrial consumption if prolonged nuclear and hydropower constraints threaten security of supply. Under the proposed extension, transmission system operator Transelectrica...

Romania transforms telecom backup batteries into virtual power plant

Romania is testing whether thousands of backup batteries installed at telecommunications sites can be transformed from emergency infrastructure into a distributed virtual power plant capable of generating revenue in electricity flexibility markets. Huawei Romania, Bamboo Energy and Flexumers are developing...
Supported byVirtu Energy