Supported byClarion Energy
HomeHydroVišegrad hydropower generation...

Višegrad hydropower generation drops in July 2026 to 30.27 GWh

July output and month-on-month comparison

Višegrad hydropower plant generated 30.27 GWh of electricity in July 2026. The figure was down 31.2% from 44.02 GWh produced in June. Output in July 2026 remained above the 25.11 GWh recorded in July 2025.

2026 cumulative generation and recent annual performance

Cumulative production at the plant reached 657.78 GWh in 2026. In 2025, Višegrad generated 781.8 GWh, compared with 733 GWh in 2024. The data indicate a stronger year-to-date trajectory relative to the preceding year figures.

Plant operator, capacity and historical generation range

The facility is operated by Hidroelektrane na Drini. Installed capacity is 315 MW, made up of three 105 MW units. The plant entered operation in 1989.

Role in regional power market dispatch and pricing

The plant has average annual production of around 1,010 GWh. Its strongest year was 2010, when generation reached a record 1,283.05 GWh. The July decline is relevant for the western Balkan power market because hydro availability is among the key variables influencing cross-border flows, thermal dispatch and wholesale prices across Bosnia and Herzegovina, Serbia and Montenegro.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Federation of Bosnia and Herzegovina raises wholesale gas price 12%

The Federation of Bosnia and Herzegovina has approved a 12% increase in wholesale natural gas costs, setting the price at €567 per 1,000 standard cubic metres, excluding VAT. The change applies retroactively from October 1. The previous price was...

Bosnia’s Gradina Wind Project Clears Screening for 100 MW

Bosnia and Herzegovina’s planned 100-MW wind energy project near Tomislavgrad has cleared an environmental screening stage, with authorities deciding that a full environmental impact assessment is not required. The Federal Ministry of Environment and Tourism issued the decision for the...

Bosnia and Herzegovina: ERS secures new loans as Ugljevik shutdown intensifies financial strain

Bosnia and Herzegovina’s state-owned power utility ERS has secured another €2 million in short-term financing, bringing the total amount of new borrowing arranged within just a few days to €7 million. The additional funds come as the company faces...