Tent power plants, unit B1 overhaul project status update

Overhaul activities regarding revitalization of Unit B1, during the past 60 days (started on 10 May) have been carried out according to the time schedule. Delivery of equipment and parts accompanies, for now, the dynamics of works on the facility. These days, on this year’s biggest construction site at CE ??N? around 800 people are engaged.

This is the conclusion from today’s, so far the second, periodical meeting of the main contractors and management of the project of revitalization TENT B1.

Zoran Stojanovic, director of TENT B and manager of this project, presented the overview of performed activities, with the percentage of their readiness, as well as the tasks ahead of this month. According to him, 30 per cent of works on turbo aggregate (lot 1) have been executed. During June, there is a pending delivery and the beginning of mounting of low pressure turbine blades. Also, the works begin on the replacement of rotor blades of medium-pressure turbine, which was transported to

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia power prices fall as regional market gaps widen

Serbian day-ahead electricity prices fell for delivery on 2 October, moving against increases recorded in most neighbouring markets. The decline widened Serbia’s price discount to Hungary, although sharp evening price peaks showed that lower daily averages did not eliminate...

Serbia: SEEPEX hits record September trading volume as electricity prices increase

Serbia’s SEEPEX day-ahead electricity market recorded its highest-ever monthly trading volume in September, while average electricity prices increased compared with August. Trading turnover reached 579,406.3 MWh, representing a 5.9% increase month on month and a 26.6% rise year on year....

MOL-NIS majority stake talks in Serbia unresolved as October deadline nears

A potential MOL acquisition of a majority stake in Serbia’s NIS remains unresolved as an October deadline approaches, even after a new US authorisation that allows negotiations to continue until 30 October. The US authorisation extends the timeframe for...
Supported byVirtu Energy