Slovenia: Additional financial aid for completion of HPP Brezice infrastructure

In order to complete the infrastructure at hydropower plant Brezice on the river Sava, the Slovenian government has approved additional funds in the amount of 12.7 million euros and extended the deadline for the completion of works until the end of summer 2022. The unfinished infrastructure that needs to be completed is related to environmental protection measures as well as flood defence on several Sava tributaries.

In addition, it also necessary to reinforce the piers on the road bridges over the Sava and deepen the riverbed in the area in question. The activities to remediate construction impacts which proved to be inadequate during the environmental impact monitoring are also pending. The allocated funding is also intended for buying the rest of the land needed to build all the unfinished infrastructure and facilities.

45 MW HPP Brezice, fourth of the five planned HPPs in the lower Sava project, has been commissioned in 2017. The construction started in 2014 and the project’s cost amounted to 260 million euro. The plant is a part of the Lower Sava river cascade project which envisages the construction of five run-of-river HPPs, which overall output should be 187 MW, where annual generation should reach 720 GWh. HPP Brezice is the largest of the five, with annual electricity generation of 161 GWh. The total cost of the construction of HPP Brezice will amount to 240 million euros and it will provide about 1 % of total electricity produced in Slovenia. The plant is operated by HESS, a subsidiary of state-owned energy company HSE.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia restarts Sostanj unit 5 to meet district heating demand

Slovenia’s Sostanj thermal power plant has temporarily restarted unit 5 as colder weather increases district heating demand. Unit 6 remains under maintenance while unit 5 is brought back into service. Heat demand has reached approximately 400 MWh a day. Unit...

Slovenia shows EV fleets can become flexible power-market assets

Slovenia has demonstrated that electric-vehicle charging can be managed as a flexible electricity portfolio, rather than treated simply as an additional source of power demand. The approach could create new business opportunities for fleet operators, aggregators, electricity suppliers and...

Slovenia advances grid digitalisation with ESA-backed satellite services

Slovenia is opening its electricity network to a new generation of commercial services based on satellite data, artificial intelligence and digital twins, potentially shifting part of future grid investment away from physical equipment and towards continuously delivered data and...
Supported byVirtu Energy