Bulgaria tenders €350 million for Yadenitsa reservoir expansion linked to Chaira

Bulgaria’s National Electricity Company, NEK, has opened a tender worth approximately €350 million to expand the Yadenitsa reservoir. The project is designed to extend the operating flexibility of the Chaira pumped-storage complex.

Storage expansion and tunnel connection

The planned works would raise active water storage to 13.4 million cubic metres from 4.2 million. The larger storage volume is intended to enable longer periods of pumping and generation within the pumped-storage operation. A 6.73-kilometre reversible pressure tunnel would connect the new reservoir with the existing Chaira reservoir.

Tender timeline and procurement structure

Prequalification applications are due by November 4. The negotiated procurement is set to proceed in two stages. Construction is limited to 60 months under the procurement framework.

Scope of contract works and site stabilisation

The contract covers the dam, tunnel, intake structures, roads, monitoring systems and associated infrastructure. It also includes stabilisation works around a fault and a nearby landslide zone.

Financing route and cost estimate

The tender value is about €100 million above an earlier estimate. Full financing remains unsecured, while the project’s EU Project of Common Interest status provides a route to seek Connecting Europe Facility support for up to 50% of eligible construction costs. The expansion is aimed at increasing storage capability rather than adding equivalent new generating capacity.

The project’s market value is linked to absorbing surplus electricity and returning it during higher-demand periods, with delivery dependent on securing financing.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bulgaria’s power market tightens as rising demand and lower renewable output erase export surplus

Bulgaria’s electricity market came under significant pressure in Week 42 as stronger domestic demand and declining renewable generation reduced the country’s exportable electricity surplus. Higher consumption and weaker solar output increased reliance on conventional power plants, tightening supply conditions...

Bulgaria launches 300 MWh Tesla battery project as energy storage expansion gains momentum

Bulgaria has begun construction of a 300 MWh battery energy-storage facility in Tvarditsa, marking the first stage of a broader investment programme worth more than €350 million. The programme includes three battery projects with a combined storage capacity of...

Bulgaria records 3.69 TWh net electricity export surplus through October 18, 2026

Bulgaria posted a net electricity export surplus of 3.69 TWh between January 1 and October 18, 2026. During the period, electricity output expanded faster than domestic consumption. Rising renewable generation contributed to offsetting lower production from coal and nuclear...
Supported byVirtu Energy