Bulgaria clears Chaira pumped-storage Unit 3 for commercial operation

Bulgaria has reached another milestone in the restoration of the Chaira pumped-storage hydropower plant, with Unit 3 officially cleared for commercial operation. The National Electricity Company (NEK) said the unit completed all regulatory and technical approval procedures required for return to service.

NEK announced that the unit received its final operating permit after an inspection by the state commission. The approval indicates that rehabilitation works satisfy technical, construction, and legal requirements. Inspectors also confirmed that the refurbishment was carried out in line with approved engineering plans and applicable standards.

Chaira Unit 3 returns to regular service

The certification completes the recovery process for Unit 3 and supports the gradual restoration of HPP Chaira toward full functionality. NEK described the clearance as enabling the facility to return to regular service following completion of rehabilitation activities. The state commission’s inspection outcome was cited as the basis for the operating permit.

The HPP Chaira site is positioned to provide balancing and flexibility services within Bulgaria’s electricity system and the wider Balkan power market. It is described as the largest pumped-storage hydropower plant in the region. The plant had been largely offline for several years after unsuccessful repair works led to shutdown of its generating units.

Ongoing restoration for Units 1 and 4

NEK continues restoration work across remaining units at Chaira. Rehabilitation for Unit 1 is being performed by Japan’s Toshiba Corporation under an agreed schedule, with completion expected in 2028. Preparations are also underway for recovery of Unit 4.

The utility is advancing a broader program aimed at fully restoring this energy storage and generation asset. NEK said the return of additional capacity at Chaira is expected to strengthen Bulgaria’s ability to balance renewable energy production. It also cited improvements to grid reliability and overall energy security across the region.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Renalfa upgrades Devnya solar to 65 MWp with 165 MWh battery storage

Renalfa IPP has expanded its Devnya solar plant in Bulgaria from 5 MWp to 65 MWp and paired the site with a 60 MW/165 MWh battery. The upgrade increases photovoltaic capacity at the location by roughly thirteenfold. It also...

Renalfa boosts Devnya solar to 65 MW with 60 MW/165 MWh battery

Renalfa has expanded its Devnya solar project in northeastern Bulgaria, increasing generation capacity from 5 MW to 65 MW. The upgrade adds a new 60 MW/165 MWh battery to the site. The project is already connected to the grid. Renalfa...

Bulgaria generation up 11% on renewable growth through Sept. 20

Bulgarian electricity generation increased 11.33% year on year to 32.61 TWh between Jan. 1 and Sept. 20, with the rise supported by stronger renewable output. Domestic electricity consumption climbed 8.19% to 29.48 TWh over the same period. The resulting...
Supported byVirtu Energy