Bulgaria has reached another milestone in the restoration of the Chaira pumped-storage hydropower plant, with Unit 3 officially cleared for commercial operation. The National...
The Bulgarian energy sector has taken a significant step towards bolstering its electricity grid stability with the restoration of an additional generating unit at...
The rehabilitation of Bulgaria's Chaira Pumped-Storage Hydropower Plant is advancing, with key units nearing operational readiness. Caretaker Energy Minister Traicho Traikov visited the facility...
Bulgaria’s pumped-storage hydropower plant Chaira has reached a significant milestone in its ongoing modernization. In mid-May, Unit 2 officially received final regulatory approval, marking...
The National Electricity Company (NEK) has confirmed that unit 2 at the Chaira pump-storage hydropower plant in southwestern Bulgaria successfully completed a 72-hour testing...
Serbia has secured a $600 million World Bank framework for a gas-system overhaul. The programme is planned as a decade-long modernisation of Serbia’s gas...
Bulgargaz, the Bulgarian state-owned gas supplier, has secured a 10-year wholesale gas licence in Serbia. The permit authorises the company to conduct commercial gas...
North Macedonia’s gross electricity generation declined 22.3% year on year to 460,035 MWh in July, even as hydro and wind output increased. The month’s...