Supported byClarion Energy
HomeNews Serbia EnergySerbia: EPS Supervisory...

Serbia: EPS Supervisory board adopted Annual Business Program, financial and investment plans 2014

Contracted prices for the delivery of electricity to the qualified buyers are at a higher level than those originally planned. – The yield from electricity has increased by 7.2 billion RSD. – adopted ABP for 2014 should soon be approved by the Ministry and adopted by the Government of Serbia.

At the meeting of Supervisory Board of the public enterprise “Electric Power Industry of Serbia“, held on February 19, presided by prof.dr. Aca Marković, president of SP JP EPS, the Annual Business Program of JP EPS for 2014 is adopted, as well as the programs of dependent companies. In addition to the members of SB, the meeting was attended by the members of the management of EPS, directors and representatives of companies.

As it was stated at the SB meeting, a new Annual business program for 2014 has been agreed with macroeconomic presumptions and data from the fiscal strategy for 2014 and including projections for 2015 and 2016, disclosed in December last year, after the adoption of the original version of ABP. The data in the adopted ABP were affected by the current conditions in the electricity market.

– As the contracted prices for  electricity delivery  to qualified buyers are at a higher level than those originally planned, so the electricity yield has increased by 7,2 billion dinars –  it was stated at the meeting  – News concerning ABP are related to two hydro power plant that are within the company “Drinsko-Limske HPPs“ that have the status of privileged electricity producers.

By the new plan, total incomes are enlarged by 6,9 billion RSD, to 240 billion RSD, while the expenditures are reduced by 5,8 billion RSD and amount to 240 billion RSD as well. According to Mr. Dejan Trifunović, assistant minister of energy and a member of EPS SB, adopted ABP for 2014 should soon be approved by the Ministry and afterwards by the Government of Serbia.

The director for internal audit and control of the business system  of “Electric Power Industry of Serbia“, Mr. Jovan Koprivica has introduced the members of SB with the Report of the State Audit Institution on the conducted audit of financial reports of JP EPS and with the proposal of Feedback Report. The members of the Supervisory Board of JP EPS have considered  and accepted the initiative for merging  the Company “Autotransport“ to the “TE-KO Kostolac“.

Milan Vujaković, the coordinator for legal issues of investments in the production, in the Department of strategy and investments of EPS and a member of the Working Group for the  implementation of Energy Agreement, achieved in the technical dialogue of Belgrade and temporary institutions of self-government in Priština, informed the SB members on the current situation. Mr. Vujaković has pointed out that the Working Group has concluded at the meeting held on February 5, that the activities related to formation of the new energy subject should be continued in the north of Kosovo and Metohija in order to realize obligations undertaken from the technical dialogue.

Source; Serbia Energy

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungary and Serbia electricity prices surge as SEE import dependence grows and German price gap widens

Southeastern European day-ahead electricity markets showed sharp price divergence on Thursday, with Hungary and Serbia trading above €260/MWh as stronger demand, tighter regional supply and continued reliance on imports pushed prices higher. At the same time, electricity prices declined...

Greece moves forward with first biomethane production facility

Greece is moving ahead with the development of its first biomethane production facility, following the issuance of an installation permit to DEPA Trade for a renewable gas unit at an existing biogas plant in Epirus. The project will be developed...

Slovenia’s Brežice Solar Complex Reaches 15.34 MW

HESS, Slovenia’s hydropower producer, has commissioned two solar facilities at the Brežice hydropower plant, bringing total photovoltaic capacity at the site to 15.34 MW. HESS describes the expanded facility as Slovenia’s largest solar complex. The new installations are named...