Serbia’s state-owned power utility EPS has opened a formal channel to acquire or partner with privately developed renewable energy projects of at least 50 MW, creating a potential exit opportunity for developers as grid access, financing and market conditions...
EPS procurement update ahead of international construction tender
Serbia’s state power utility EPS has launched a consultancy tender to revise procurement documents for the planned 660 MW Bistrica pumped-storage hydropower plant before an international construction tender. The existing procurement documentation...
Serbian state-owned utility EPS has launched procurement for additional professional supervision at the 66 MW Kostolac wind farm. The contract is valued at approximately €275,000. The procurement was launched on 5 September 2025.
Scope of the supervision contract
The supervision decision...