EPS secures €107.5 million for hydro upgrades and coal-site solar in Serbia

EPS, Serbia’s state utility, has secured approximately €107.5 million to modernise hydropower plants and develop more than 120 MW of solar capacity on land tied to former coal-fired facilities. The financing package combines a €100 million European Investment Bank loan agreed in 2024 with about €7.46 million in grants from the Western Balkans Investment Framework. The programme is designed to support both generation upgrades and new solar development.

Financing structure for hydropower modernisation and solar build-out

The European Investment Bank component totals €100 million, with the agreement reached in 2024. Additional funding of about €7.46 million is provided through grants under the Western Balkans Investment Framework. Together, the loan and grants underpin the investment plan for hydropower upgrades and associated solar capacity.

A substantial part of the programme will be directed to upgrading generating units at the Bistrica, Potpec and Djerdap II hydropower plants. Potpec is also due to receive an additional 13 MW unit as part of the works. The investment package further includes rehabilitation of the 129 MW Vlasinske hydropower cascade.

EPS is considering ash-disposal areas and coal-storage sites linked to the Morava and Kolubara A thermal power plants for solar construction after their closure. The projects are described as being at an early development stage. The approach targets land associated with retired thermal assets.

The use of former thermal power sites for solar generation could enable EPS to reuse existing land and grid infrastructure while reducing permitting and connection challenges. Modernising hydropower is also intended to provide more flexible renewable capacity to balance growing solar and wind production.

Funding scale relative to Serbia’s generation fleet

The funding is characterised as material but modest compared with the scale of EPS’s coal dependence and ageing generation fleet. The outcome is described as dependent on execution, including how quickly projects move from financing agreements to operating megawatts.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia plans North Macedonia gas interconnector construction start, aiming Q1 2028

Pipeline scope and early works near Vranjska Banja Serbia is targeting early 2028 completion for its gas interconnector with North Macedonia, with construction planned to start and reach completion in the first quarter of 2028. Initial works near Vranjska Banja...

EBRD considers senior loan for ENNA’s Mihailesti solar-plus-storage in Romania

The European Bank for Reconstruction and Development is reviewing a potential senior loan for ENNA Group’s Mihailesti solar and storage project in southern Romania. The bank’s financing decision is expected by early November. The proposed loan amount has not...

Innovagrid secures 200 MW TCL SunPower solar modules for Serbian projects

Innovagrid has secured a supply agreement for approximately 200 MW of TCL SunPower solar modules tied to projects expected to advance in Serbia over the next year. The deal includes an initial 20 MW shipment that has been dispatched,...
Supported byVirtu Energy