Supported byClarion Energy
HomeSEE Energy NewsRomania: Eurowind got...

Romania: Eurowind got permit for Galati wind farm

Danish company Eurowind has obtained all the necessary permits, including the one for the connection to the network, for its 66MW wind farm in Galati, in the eastern part of Romania, a project worth almost 100 million euros.

EWE Frumusita, the project company in charge of the development of the wind farm, obtained the network connection contract from Distributie Energie Electrica Româania (DEER), part of the Electrica group – the manager of the network in the region where the investment would be made.

Danish group Eurowind Energy is active in wind project development in Denmark, Sweden, Germany and Romania.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...
Supported byVirtu Energy