Romania, EC Oltenia and ALRO to jointly build gas-fired power plant at Isalnita

Romanian aluminium producer ALRO said that it was declared as selected investor at the tender for the construction of gas-fired power plant at Isalnita, launched by state-owned electricity producer Energy Complex (EC) Oltenia.

Chairman of the Board of Directors at ALRO Marian Nastase said that this partnership will offer the company the opportunity to diversify its business model, as the security of supply for electricity is a must for the aluminium industry and will support its long-term development plans in a very challenging business environment.

EC Oltenia is planning to build 850 MW gas-fired power plant that will replace two (315 MW each) coal-fired units of TPP Isalnita.

For about two years, EC Oltenia has been looking for partners for ten major investment projects in new electricity generation capacity, part of the restructuring and modernization plan approved in January 2022. The contract for nine of these projects have been awarded, which includes eight solar power plants (four will be built in partnership with OMV Petrom and the other four with Tinmar Energy), while the contract for the construction of gas-fired power plant at Turceni was signed with Tinmar Energy.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romgaz gas sales fall 5.6% in Romania over nine months

Romania’s state-controlled gas producer Romgaz reported lower natural gas production and sales in the first nine months of 2026, while electricity generation was broadly stable. Domestic gas sales fell 5.6% year on year to approximately 3.43 billion cubic metres....

Romania Eyes 15 November Restart for Cernavoda Reactor

Romania could bring one of the two reactors at the Cernavoda nuclear power plant back online around 15 November, after improved Danube flows eased the water shortage that forced the units to shut down. Energy Minister Dumitru Chisalita said river...

OMV Petrom, Renovatio commission 130 MW of solar capacity in Romania

OMV Petrom and Renovatio have commissioned three solar plants in Romania with combined capacity of 130 MW. The projects at Tandarei, Bucovat and Cazanesti are supplying electricity to the national grid. OMV Petrom’s ownership stakes account for roughly 65...
Supported byVirtu Energy