Romania, Delgaz Grid to invest 5.7 million euros in modernization of three substations

Romanian electricity and natural gas distributor Delgaz Grid, a local subsidiary of German E.ON, said that it will invest 5.7 million euros in the modernization of three 110/20 kV substations in Suceava, Dorohoi and Bucecea counties.

The statement from the company said that the project involves the replacement of high and medium voltage equipment, following a European co-financing of 4.1 million euros. Also, the necessary conditions will be created for the integration in SCADA system of the three transformer stations.

The main objective of the works is to increase the security of taking over the electricity produced from renewable resources by reducing the number of interruptions, reducing the amount of undelivered electricity and reducing the maintenance costs of the distribution network. At the same time, the quality of the distribution service will be improved for almost 50,000 customers who are supplied through the stations included in the project.

The investment is co-financed with some 4.1 million euros from the European Regional Development Fund REACT-EU and the difference of 1.6 million euros is the contribution of Delgaz Grid.

Accessing European funding sources is a priority for Delgaz Grid in order to achieve the objectives of modernizing and digitizing the electricity distribution infrastructure. At the moment, seven projects, worth about 37 million euros, with a co- financing of over 28 million euros, are in different stages of implementation.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...
Supported byVirtu Energy