North Macedonia modernizes key power transmission link with Bitola–Prilep line trial operation

The energy landscape in North Macedonia has taken a significant step forward with the successful trial operation of the modernized Bitola–Prilep power transmission line. This upgraded 110 kV transmission line, which has been operational for over 50 years, underwent extensive reconstruction and was re-energized at the end of 2025, representing a critical enhancement to the nation’s electricity infrastructure.

This project involved the connection between the Bitola 1 and Prilep 1 substations along the existing route. The previous reinforced concrete towers were dismantled and replaced with robust steel lattice pylons, thereby significantly improving both reliability and structural integrity of the line.

The newly constructed line spans 33.5 kilometers and is supported by 125 steel towers. Alongside this structural upgrade, a comprehensive renewal of the electrical system was undertaken, which included new phase conductors, ground wires, insulators, and auxiliary equipment. These enhancements are expected to markedly boost electrical performance and mechanical resilience.

According to the national transmission system operator, MEPSO, this modernization will enhance the safety, stability, and operational flexibility of North Macedonia’s national grid. The upgraded corridor is anticipated to play a pivotal role in improving system reliability while accommodating future increases in electricity demand.

The reconstruction project was part of Lot 1 of MEPSO’s comprehensive grid investment program and was financed through a loan from the European Bank for Reconstruction and Development (EBRD). The construction, electrical installation, and engineering work were executed between 2023 and 2025 by a consortium led by Croatian firm Dalekovod, which adhered to all contractual and technical requirements throughout the project.

Following thorough inspections and successful testing phases, the line has now been energized and placed into trial operation. MEPSO emphasized that this initiative is part of its ongoing strategy to systematically upgrade and reinforce North Macedonia’s transmission infrastructure, thereby enhancing the security of electricity supply while increasing overall capacity and robustness within the national power system.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

North Macedonia targets 2027 construction start for €1.5 billion Čebren-Galište hydro project

North Macedonia is targeting a 2027 construction start for the long-planned Čebren and Galište hydropower projects, reviving a combined investment of up to €1.5 billion after years of unsuccessful concession attempts. Čebren is planned with a capacity of around 333...

North Macedonia eyes 2027 construction start for Čebren-Galište hydro complex

2027 target and combined investment North Macedonia is targeting a 2027 construction start for the long-planned Čebren and Galište hydropower projects. The government said the renewed push would revive a combined investment of up to €1.5 billion following repeated failed...

ESM launches third phase of €46 million upgrade for six North Macedonia hydropower plants

North Macedonia’s state-owned utility ESM has started the third phase of a programme worth roughly €46 million to modernise six large hydropower plants. The initiative is designed to upgrade existing generating assets rather than build new capacity. Capacity and...
Supported byVirtu Energy