North Macedonia modernizes key power transmission link with Bitola–Prilep line trial operation

The energy landscape in North Macedonia has taken a significant step forward with the successful trial operation of the modernized Bitola–Prilep power transmission line. This upgraded 110 kV transmission line, which has been operational for over 50 years, underwent extensive reconstruction and was re-energized at the end of 2025, representing a critical enhancement to the nation’s electricity infrastructure.

This project involved the connection between the Bitola 1 and Prilep 1 substations along the existing route. The previous reinforced concrete towers were dismantled and replaced with robust steel lattice pylons, thereby significantly improving both reliability and structural integrity of the line.

The newly constructed line spans 33.5 kilometers and is supported by 125 steel towers. Alongside this structural upgrade, a comprehensive renewal of the electrical system was undertaken, which included new phase conductors, ground wires, insulators, and auxiliary equipment. These enhancements are expected to markedly boost electrical performance and mechanical resilience.

According to the national transmission system operator, MEPSO, this modernization will enhance the safety, stability, and operational flexibility of North Macedonia’s national grid. The upgraded corridor is anticipated to play a pivotal role in improving system reliability while accommodating future increases in electricity demand.

The reconstruction project was part of Lot 1 of MEPSO’s comprehensive grid investment program and was financed through a loan from the European Bank for Reconstruction and Development (EBRD). The construction, electrical installation, and engineering work were executed between 2023 and 2025 by a consortium led by Croatian firm Dalekovod, which adhered to all contractual and technical requirements throughout the project.

Following thorough inspections and successful testing phases, the line has now been energized and placed into trial operation. MEPSO emphasized that this initiative is part of its ongoing strategy to systematically upgrade and reinforce North Macedonia’s transmission infrastructure, thereby enhancing the security of electricity supply while increasing overall capacity and robustness within the national power system.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

North Macedonia June generation drops 13.2% as solar output declines

North Macedonia’s gross electricity production decreased 13.2% year on year to 408,045 MWh in June. The figures were released against a backdrop of drought and high temperatures affecting system operation. Electricity from thermal power plants totaled 131,405 MWh, down...

Serbia–North Macedonia gas interconnector enters implementation phase, linking to Greek LNG

Serbia and North Macedonia have moved their planned gas interconnector into the implementation phase. The project is designed to strengthen a northbound supply route connecting the Serbian market with Greek LNG infrastructure and the Southern Gas Corridor. Implementation agreement...

North Macedonia to join Vertical Gas Corridor in September

North Macedonia plans to join the Vertical Gas Corridor in September. The move is aimed at shifting the country’s gas system from a relatively isolated national network to a wider north-south supply route across Southeast Europe. The corridor entry...
Supported byVirtu Energy