Croatia’s Gas Storage Levels Significantly Below Seasonal Norms Amid LNG Terminal Shutdown

Croatia’s main underground gas storage facility, Okoli, has entered mid-January with stock levels significantly below the seasonal average, primarily due to a combination of harsh winter conditions and the recent temporary shutdown of the Krk LNG terminal. Currently, Okoli is approximately 32% full, translating to about 1.51 billion kWh of natural gas. This figure starkly contrasts with last year’s levels, where the facility registered close to 51% fullness at the same time.

The situation in Croatia is particularly concerning when compared to the broader European context, where underground gas storage sites are around 55% filled. The decline in Croatia’s storage capacity is notably steeper than the EU average, indicating a potential vulnerability in the country’s energy supply.

Officials attribute this low storage balance largely to the prolonged interruption of operations at the Krk LNG terminal, which was undergoing upgrades. The Ministry of Economy has emphasized that winter supply security is contingent not only on storage volumes but also on a comprehensive strategy that includes LNG imports, cross-border pipeline flows, and domestic gas production capabilities.

Prior to the terminal’s shutdown for enhancements, Okoli had been filled above EU averages until early September last year. The outage at Krk necessitated increased reliance on storage withdrawals to maintain supply continuity through mid-November 2025. During this period, the terminal was offline for over six weeks as its regasification capacity was expanded from 3.9 billion to 6.1 billion cubic meters per year.

Despite these challenges, officials have noted that the Krk terminal has resumed operations with enhanced throughput. This development is expected to bolster long-term supply security not only for Croatia but also for neighboring markets as they navigate through winter demand challenges.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Acciona Energia commissions 72 MW Croatian wind under 12-year contracts for difference

Acciona Energia has commissioned 72 MW of wind capacity in Croatia under 12-year contracts for difference, expanding its operating footprint as it develops large-scale solar. The commissioning brings the company’s Croatian operating portfolio to 102 MW across three wind...

Croatia amends Electricity Market Act to expand aggregation, grid studies, and connection rights

Croatia’s amended Electricity Market Act entered into force on October 15, 2026, introducing changes that go beyond conventional electricity-market reform. The legislation reshapes the commercial roles for industrial flexibility, the preparation of grid-connection studies, and the duration of legacy...

Croatia electricity generation up 13% in August 2026, imports still high

August 2026 generation mix and year-on-year increase Croatia’s electricity production rose 13% year on year to 1,262 GWh in August 2026, according to figures from the Croatian Bureau of Statistics. The data show output increasing from 1,117 GWh in August...
Supported byVirtu Energy