Macedonia, Fire at unit 3 of TPP Bitola

Due to a fire, which broke out in the evening of 6 November, unit 3 of coal-fired thermal power plant Bitola has been shut down.

The broke out at one of the unit’s transformers and it was quickly extinguished. However, the unit was shutdown since the procedure in case of a fire is automated.

TPP Bitola, with its two operational units, covers about 70 % of electricity consumption in North Macedonia.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

ESM launches third phase of €46 million upgrade for six North Macedonia hydropower plants

North Macedonia’s state-owned utility ESM has started the third phase of a programme worth roughly €46 million to modernise six large hydropower plants. The initiative is designed to upgrade existing generating assets rather than build new capacity. Capacity and...

North Macedonia aims for 38% renewables share by 2030

North Macedonia is targeting 38% renewable energy as a share of gross final energy consumption by 2030. The programme includes rapid solar expansion and additional hydropower generation, with parts of the plan reported to be ahead of the planned...

North Macedonia generation drops 22% in July as renewables rise

North Macedonia’s gross electricity generation declined 22.3% year on year to 460,035 MWh in July, even as hydro and wind output increased. The month’s generation mix included higher contributions from hydropower and wind compared with the same period a...
Supported byVirtu Energy