Hungary, No further extensions were permitted and OAH requested the project company to submit supplementary application

The National Atomic Energy Office (OAH) said that the documentation submitted for the project for the expansion of nuclear power plant Paks by building two additional reactors is not convincing enough for the issuance of the implementation permit by the regulator.

The deadline for the issuance of the permit expired on 30 September. As it was already extended by three months, no further extensions were permitted and OAH requested the project company to submit supplementary application.

The statement from the OAH said that the documentation submitted is very thorough in many respects, but in order for the authority to be satisfied that all the requirements are fully met, further assessment and analysis are needed in some areas, taking into account the recommendations from the IAEA mission carried out in parallel with the licensing process. To this end, the OAH will order a further completion of the licensing procedure.

With this delay, it is very unlikely that the new units will be operational before 2030, when the permits for the operation of the two existing reactors expires. MVM, the plant’s operator, is already considering the extension of their operational life.

The delay also means that the Russian 10 million euros loan taken for the expansion project will have to be repaid starting from 2031 instead of 2026, thus decreasing its maturity by five years.

In January 2014, Hungarian Government has signed deal with Russia`s Rosatom, with a goal to increase output of the power plant, from current 2,000 MW to 4,400 MW by adding two more reactors. Under the agreement, Russia will provide 10 billion euros loan for the construction of new unit in existing NPP, which is around 80 % of estimated construction cost. According to initial plan, first unit was supposed to become operational in 2023.

Currently, NPP Paks provides about a half of Hungary’s total electricity generation and the new nuclear capacity will be even more significant following the closure of coal-fired TPP Matra.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungary: HUPX day-ahead power prices jump 24% in August as trading volumes rise

Hungarian day-ahead electricity prices rose significantly in August, while trading volumes increased both month on month and year on year, reflecting stronger activity on the country’s wholesale power market. The average HUPX day-ahead baseload price reached €152.17/MWh, marking a 24.4%...

Paks II commissioning timeline uncertainty as Hungary’s nuclear replacement window tightens

Paks II schedule risk extends into 2035 Hungary’s Paks II nuclear expansion could see completion pushed to 2035, according to an internal construction timetable cited in a report. The same source indicates the project could be delayed until 2035, narrowing...

Hungary tenders 702 MVA grid capacity for new wind projects

Hungary has launched a tender for 702 MVA of grid connection capacity reserved for new wind projects. The allocation is intended to reopen access to grid capacity after a period in which wind development remained largely frozen while solar...
Supported byVirtu Energy