Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level

Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level in the plant’s intake basin reaches 1.58 metres. Authorities said the approach is designed to respond as river conditions change.

The first stage involves positioning loaded vessels and barges across about 600 metres of the river. The objective is to redirect additional water toward the Danube-Black Sea Canal and the Cernavoda intake. This step would be applied before moving to more extensive works.

Temporary closure structure and pumping options

If the initial redirection is not sufficient, authorities could build a temporary closure structure of around 170 metres near the connecting canal. Pontoons and barriers are described as the preferred option, while a temporary stone dam is also being considered. The plan therefore includes multiple engineering alternatives depending on effectiveness.

As a final measure, high-capacity pumps would be used to transfer additional water directly toward the cooling intake. Both Cernavoda units are currently offline, with operators maintaining focus on cooling-water availability rather than generation restart timing.

Current river conditions and cooling requirements

The Danube level in the area has fallen to around 1.86 metres. Forecasts indicate below-average flows through September, October and November, extending the period of constrained water availability. Adequate cooling water remains necessary even when reactors are not generating electricity.

Authorities also cited earlier attempts to improve water availability, including blasting a rock formation and sinking barges to redirect river flows. Those actions did not provide a lasting solution. Any return to nuclear generation would depend heavily on whether Danube conditions improve.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania Competition Council clears NIS Petrol acquisition by Argenta

Romania’s Competition Council has approved the acquisition of NIS Petrol by Romanian company Argenta, removing a regulatory obstacle to NIS’s planned withdrawal from the Romanian market. The decision comes as pressure continues over the Serbian oil group’s Russian ownership....

Transelectrica completes €51 million STATCOM voltage control upgrade ahead of schedule

Romanian electricity transmission operator Transelectrica has completed a €51 million investment in voltage control infrastructure. The project is designed to strengthen the national grid’s ability to accommodate additional renewable generation and manage fluctuations in electricity flows. Transelectrica said the...

Romanian electricity demand down 4% in 2026 amid near-48% solar growth

Consumption trends across customer groups Romanian electricity consumption declined by 4% in the first eight months of 2026, according to data published by the National Institute for Statistics. Total electricity use reached 32.02 TWh between January and August, compared with...
Supported byVirtu Energy