Greece: Rejection of environmental permit for island wind project Aigaio

The so-called Aigaio 486 MW wind project worth 1.5 billion euros failed to obtain environmental permit. The Greek Ministry of Energy and Environmental protection has rejected the environmental permit application for the project to be constructed on uninhabited islands in the Aegean Sea.

The application was submitted by Eunice Energy Group’s subsidiary Cycladic Meltemia. In its explanation of the rejection, the Ministry said that the project would cause lasting environmental damage. The ruling is issued following many months of public consultations regarding the project’s environmental impact.

According to the ruling, the application could not ascertain that the installation of the wind farm consisting of 106 turbines would not harm the integrity of the sites and the environment of the 14 islands. A major reason for the rejection was also the potentially harmful effects that the turbines would have on migratory birds. In addition, the project’s spatial plan overlaps with protected or special conservation zones within the Natura 2000 network.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece moves forward with first biomethane production facility

Greece is moving ahead with the development of its first biomethane production facility, following the issuance of an installation permit to DEPA Trade for a renewable gas unit at an existing biogas plant in Epirus. The project will be developed...

Croatia to auction guarantees of origin for wind, solar and biomass on Oct. 27

Croatia will hold a new round of guarantees of origin auctions on Oct. 27, with certificates linked to wind, solar and biomass generation. The auction process involves HROTE, ENNA Next, KOER and CROPEX. The certificates are intended to expand...

Greece LNG-driven exports jump 169% in first nine months of 2026

Greece’s natural gas exports rose by almost 169% in the first nine months of 2026, reaching 13.60 TWh between January and September. Exports were up from 5.06 TWh in the corresponding period of 2025. Total demand, including exports, increased...
Supported byVirtu Energy