Greece, HEDNO – increasing the network capacity by 5 GW by 2025 to accommodate RES units

Greek distribution network operator DEDDIE/HEDNO plans to increase network capacity by 5 GW, to 13.5 GW by 2025, to facilitate the production of renewable energy sources, Dimitris Vranis, director of the Network Users Department, said at an industry event in Thessaloniki.

As a result, the target for increasing capacity set in the revised National Energy and Climate Plan (NECP) for 2030 would be exceeded, Vranis noted, at the annual event organized by POSPIEF, the Pan-Hellenic Federation of Photovoltaic Manufacturers Associations.

The NECP has set a target of 25 GW for the connection of RES units by 2030.

Given that half of the RES units that should be connected are expected to be connected to low and medium voltage connections, the distribution network will have to be able to accommodate projects with a total power of 12.5 GW.

Considering this projection, the goal of the distribution network operator to increase the capacity of the distribution network to 13.5 GW by 2025 exceeds the required capacity by 8 percent.

In addition, in the period from 2025 to 2030, DEDDIE/HEDNO plans to further increase the network capacity by another 2 GW, to 15.5 GW.

Currently, renewable energy plants with a total capacity of 6.5 GW are connected to the Greek distribution network, said the DEDDIE/HEDNO official.

About 7,000 small RES projects are currently being developed in Greece, with a total capacity of about 2 GW. Most of these projects are photovoltaic installations, and 5,300 units are privately owned and have a capacity of about 400 MW.

Sign up for updates & special reports

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Faria Renewables acquires 23.1 MW Greek wind farm

Greek developer Faria Renewables has completed the purchase of a 23.1 MW wind farm in Boeotia from EDP Renewables. The acquisition adds an operating renewable asset to Faria’s portfolio. It is the first of two wind projects included in...

Greece adds 2.7 GW of renewables as solar curtailment grows

Greece connected around 2.7 GW of new wind projects and solar capacity in the first ten months of 2026, bringing its renewable portfolio to roughly 19 GW. About 2.1 GW of the additions was solar and 600 MW was...

Crete-Cyprus Interconnector Advances to Seabed Surveys

Survey teams are preparing to examine the seabed along the proposed submarine cable route for the Great Sea Interconnector between Crete, Greece, and Cyprus. The French research vessel Abeille Marengo has arrived in Crete and is waiting for authorisation...
Supported byVirtu Energy