The planned gas interconnection between Bosnia and Herzegovina and Croatia is facing further delays as AAFS Infrastructure and Energy commissions a feasibility study of alternative pipeline routes. The project is intended to diversify Bosnia and Herzegovina’s gas supply by providing access through Croatia and reducing reliance on Russian imports. Estimated at around €1.5 billion, it remains held back by property disputes, financing questions and incomplete contractual arrangements.
AAFS Bosnia director Amer Bekan said an international consultant had been engaged to carry out a new assessment costing around $10 million. The study will focus on parts of the previously planned route that can no longer be used.
Property and project documentation remain unresolved
Bosnia and Herzegovina’s unresolved dispute over state property is also affecting the project. Authorities in Republika Srpska argue that public land should belong to the entities, while officials in the Federation support retaining ownership at state level.
Earlier technical studies, financed by the European Union, were prepared when BH-Gas was expected to develop the project. Approval to transfer the documentation to the new investor has not been secured.
Construction financing and timeline uncertain
AAFS joined the project through an arrangement facilitated by the U.S. Embassy in Sarajevo, but has not secured construction financing. Banks, investment funds and other financial institutions are expected to participate, although no final financing package has been announced.
A construction start in 2027, indicated previously, is increasingly uncertain. Former BH-Gas director Almir Becarevic has said completion before 2030 is unlikely.