The subsidiary of the power utility ERS, “Hidroelektrane na Drini”, which operates the Visegrad hydropower plant, announced that the plant generated 73.18 GWh of electricity in December 2024. This marks a 37.5% increase compared to the previous month, when production stood at 53.22 GWh. However, the plant’s output in December 2024 was lower than the 150.81 GWh produced in the same month of the previous year.

In total, HPP Visegrad produced 733 GWh of electricity in 2024, down from 1,224 GWh in 2023. Commissioned in 1989, the plant has a power output of 315 MW (3 x 105 MW) and typically generates an average of 1,010 GWh annually. The plant’s record annual production was achieved in 2010, with a total of 1,283.05 GWh.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bosnia’s Gradina Wind Project Clears Screening for 100 MW

Bosnia and Herzegovina’s planned 100-MW wind energy project near Tomislavgrad has cleared an environmental screening stage, with authorities deciding that a full environmental impact assessment is not required. The Federal Ministry of Environment and Tourism issued the decision for the...

Bosnia and Herzegovina: ERS secures new loans as Ugljevik shutdown intensifies financial strain

Bosnia and Herzegovina’s state-owned power utility ERS has secured another €2 million in short-term financing, bringing the total amount of new borrowing arranged within just a few days to €7 million. The additional funds come as the company faces...

EPBiH coal shortages raise risk of further electricity tariff pressure in 2026-2027

EPBiH, the state-owned power utility in Bosnia and Herzegovina, faces renewed electricity-price pressure as coal supply problems contribute to losses. The company could see pressure for another electricity-price increase by late 2026 or early 2027, according to the conditions...