Bosnian state-owned power utility EPBiH adopted a report on the company’s operations in 2021. Key elements are that electricity generation reached 6,677 GWh in 2021, 7 % more than in 2020, while consumption in its supply area increased by 3.5 % year-on-year.

EPBiH’s net profit in 2021 amounted to 6.3 million euros, of which 1.2 million euros will be distributed as dividends, while the remaining 5.1 million euros is allocated to reserves.

With investments exceeding 50 million euros, EPBiH was one of the largest investors in Bosnia and Herzegovina in 2021. However, the realized investments were noticeably lower than planned. In addition, EPBiH invested about 4 million euros in its coalmines through recapitalization.

Regarding projects, the construction of Podvelezje wind farm, the first wind farm owned by EPBiH, was completed in March 2021. The company also launched and completed preparatory works for the construction of unit 7 at coal-fired thermal power plant Tuzla.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

EU CBAM revisions could cut Bosnia electricity exporters’ costs by up to €13 million

Proposed changes to the European Union’s Carbon Border Adjustment Mechanism could reduce the cost faced by Bosnia and Herzegovina’s electricity exporters by as much as €13 million annually. Bosnia says the revisions could save exporters €13 million a year,...
Supported byVirtu Energy