TENT(Power Plants Nikola Tesla) Electricity production plans achieved

 

Economic Association “Thermal Power Plants Nikola Tesla” produced and delivered 1.424.052.000 kWh to power system in August 2011, 14, 16% less than planned.  Nine outages were recorded in total in this month, three of them in TPP “Nikola Tesla A” (TENT A), four in TPP “Kolubara” and two in TPP “Morava”.

TENT A produced and delivered 851.624.000 kWh to the power system, 3,6% more than planned. Units A1 and A6 were this month continuously on the grid, while the unit A4 was on the grid the longest period of time in this year. It was continuously on the grid 180 days (4311,82h) and broke the previous  record that unit A1 held. Unit A4 is in the expended overhaul period since July, 26th.

In the same period, TENT B generated 429.384.000 kWh, 36,48% less than planned. The main reason for unrealized energy balance, as stated in the report, was delayed start of the other 620MW unit overhaul. According to the schedule, the unit overhaul should have lasted in the period from 01.05. to 08.08.2011. but started on May, 14th. Unit B1 was in August continuously on the grid.

TPP “Kolubara” produced and delivered 86.941.000 kWh to the power system and realized 94,5% of the plan, 5,5% less than planned. Unit B3 is in the overhaul phase since the beginning of 2010, and unit A4 is in the state of cold reserve from 15th of November, 2009.

TPP “Morava” produced and delivered 56.104.000 kWh to the power system and realized 81,31% of the plan.

Railway transport in the same period transported 2.626.744t of coal for the needs of TENT A, TENT B and TPP “Kolubara”, 1,43% less than planned.

Specific liquid fuel consumption of TENT ltd. is by 74, 75% lower than the norms which amount to 2.80 g/kWh.

Participation of TENT ltd in the total production of Electric power industry of Serbia is 47,64%, while the participation in the production of all power plants in the system amounts to 60,94%. If we look at the production of the TENT ltd in relation to the Public company “Electric Power Industry of Serbia” without TPP “Kosovo”, percentages are significantly larger and amount to 55,66%, that is 74,71%.      

Source: Tent Magazine

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungary leads SEE power-price surge as lower wind tightens Monday market

Hungarian electricity prices for Monday delivery surged as weekday demand recovered and wind generation declined, creating a high-price zone across Central Europe and widening price spreads with the southern Balkans. The HUPX baseload power price rose by €88.80/MWh from Sunday...

HSE construction permit for 1.38-MW solar and 1.25-MW/5-MWh battery in Zagorje ob Savi

Slovenian power utility HSE has secured a construction permit for a solar and battery project at the former Kamnolom Zagorje municipal landfill in Zagorje ob Savi. The development is linked to plans for site redevelopment in 2027. Planned generation,...

OMV Petrom to add 20-MW/40-MWh battery at Ișalnița solar site

OMV Petrom plans to add a 20-MW/40-MWh battery to its Ișalnița solar project in Romania, converting the development into a hybrid renewable generation and storage facility. The battery addition is linked to the Ișalnița site in Dolj county. Battery...
Supported byVirtu Energy