Serbia: Power utility EPS TPP Nikola Tesla TENT A FGD project to be resumed?

By the decision of the Energy Community Ministerial Council dated October 2013, the LCPD implementation has been postponed until 1st January 2024. In this way, the situation has been avoided in which energy security would be jeopardized by the closing down of thermal power facilities with the capacity below 300 MW for which replacement capacities have not been provided and there is no economic justification for applying the expensive measures for reducing emissions. There would also be a problem for the plants in which the environmental protection activities cannot be concluded within the originally set deadline – 1st January 2018.

With the aim of the LCPD implementation, the Serbian energy company Elektroprivreda EPS is implementing or planning projects the total worth of which is 625 million euros.

The most important project of the EPS is desulphurization in TPP Nikola Tesla A, worth 170 million euros. The funds have been provided by the Japanese International Cooperation Agency JICA. The first phase of the project includes the construction of desulphurization plants for the blocks A3 and A4, and the second phase for the blocks A5 and A6.

After the conclusion of this most expensive environmental project in the region, the concentrations of sulphur-dioxide will be reduced below 200 mg/m3, which means that the limit values prescribed by the IED will be satisfied simultaneously. The project was planed be finished in 2017, but it is uncertain when the contract will be signed with the contractor, which was announced for February this year. In the tender for choosing the contractor, three bidders passed prequalification phase–Japanese consortium Mitsubishi-Hitachi, Austrian Andritz and German-Japanese company SBENGI.

The value of the project of desulphurization in TPPNT B has been estimated at around 110 million euros. The tender for choosing the contractor is being prepared.

The desulphurization in the TPP Kostolac will be carried out within the Chinese loan. The investment is worth 96 million euros and the project should be finished at the end of this year , transmits Serbia-energy.eu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungary leads SEE power-price surge as lower wind tightens Monday market

Hungarian electricity prices for Monday delivery surged as weekday demand recovered and wind generation declined, creating a high-price zone across Central Europe and widening price spreads with the southern Balkans. The HUPX baseload power price rose by €88.80/MWh from Sunday...

HSE construction permit for 1.38-MW solar and 1.25-MW/5-MWh battery in Zagorje ob Savi

Slovenian power utility HSE has secured a construction permit for a solar and battery project at the former Kamnolom Zagorje municipal landfill in Zagorje ob Savi. The development is linked to plans for site redevelopment in 2027. Planned generation,...

OMV Petrom to add 20-MW/40-MWh battery at Ișalnița solar site

OMV Petrom plans to add a 20-MW/40-MWh battery to its Ișalnița solar project in Romania, converting the development into a hybrid renewable generation and storage facility. The battery addition is linked to the Ișalnița site in Dolj county. Battery...
Supported byVirtu Energy