The construction of the Nis-Sofia gas pipeline with its 108-kilometers section in Serbian territory, should be launched in early 2021. The total value of construction works is estimated at around 85 million euros, of which 49.6 million euros were donated by the European Union.

New natural gas connection with Bulgaria will open development possibilities, new markets and options for cleaner environment. The construction will allow easy gas access for citizens and businesses of Bela Palanka, Pirot, and Dimitrovgrad – three towns that previously haven’t had access to gas.

The main objective of constructing a gas pipeline that will link existing gas systems of Serbia and Bulgaria is to increase security of natural gas supply for Serbia. Serbia is among the rare countries with only one point of supply, located on the border with Hungary. Once the Balkan Stream gas pipeline is constructed, the role of this gas pipeline will not be diminished: it will allow Serbian consumers to receive gas from other sources, existing or to be constructed in the near future.

Projected capacity of 1.8 billion of cubic meters of gas a year will meet 80 % of Serbia’s current gas needs. Furthermore, the construction of an additional compressor station in Serbia in the future would also allow reverse gas flow from Serbia to Bulgaria. This would serve as a technical precondition for the creation of a regional natural gas market with sufficient financial liquidity.

Nowadays, with environmental protection, reduction of the impact of climate change, and energy efficiency at the heart of energy policy of all countries, including the European Union, the question of appropriateness of investment in new gas installations is raised. This is a legitimate question and, in Serbia’s case, it’s easy to answer. At around 65 %, Serbia is the country with the highest share of consumption of low-calorie coal in electricity production. The inevitable reduction of coal in electricity production in Serbia and ever-larger investments in renewables, which are less predictable in terms of production planning, raise the question of balancing power production in Serbia. That is where natural gas comes in as optional transitional fossil fuel, due to smaller environmental pollution and greater flexibility in terms of power production. All of this would also allow towns and municipalities in Serbia with developed district heating systems to construct high-efficiency, small-scale combined heating and electricity generating systems.

If high costs of investment in filtration systems in coal-fired power plants and a significant drop in costs of renewable-generated electrical energy are taken into account, it becomes clear that further investment in coal-generated electricity is not justified.

Also, further integration of Serbia into the European Union requires strict application of EU measures and respect of EU directives in the area of environmental protection. All international financial institutions such as the European Investment Bank, European Bank for Reconstruction and Development, and the World Bank have stopped funding projects that involve coal as fuel, drastically reducing the possibilities to fund such projects in the capital market.

 

 

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

500 MW combined-cycle gas plant joint venture advances in Niš

Serbia’s EPS and Srbijagas have agreed with Azerbaijan’s SOCAR to set up a joint venture for a planned 500 MW combined-cycle gas power plant in Niš. The arrangement is intended to advance preparations ahead of a final investment decision....

EU support for gas storage expansions at Romania and Bulgaria facilities

Connecting Europe Facility funding for storage upgrades The European Union is supporting expansions at three gas storage facilities in Romania and Bulgaria. The upgrades are designed to increase both reserves and delivery capacity to help regional markets manage supply disruptions...

Gazprom gas extension talks in Serbia as NIS sanctions deadline nears

Serbia expects to extend its gas supply arrangement with Gazprom beyond September 30 while Russian deliveries continue. President Aleksandar Vučić said after a call with Russian President Vladimir Putin that an annex should be signed shortly. The extension’s duration,...
Supported byVirtu Energy